Construction Schemes Disruptions



S.No. District Agency Scheme Village OHT Code Disruption Type Disruption Date Expected Resolve Date Status Remark
1 Baghpat LC INFRA TAYODHI TYODHI 8362900/01 Other 14-Apr-2026 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
2 Baghpat LC INFRA Hasanpur Masoori W/S Scheme Hasanpur Masoori 20014070/01 Other 08-Dec-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
3 Baghpat LC INFRA Meetli Water Supply Scheme MEETLI 20057079/01 Other 19-Aug-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
4 Baghpat LC INFRA KHEDAKI KHERIKI 8362902/01 Other 03-Aug-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
5 Baghpat LC INFRA Vazidpur wss Vazidpur 20060344/01 Other 23-Jul-2025 - Resolved NOCs from PWD is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme