| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Baghpat | LC INFRA | TAYODHI | TYODHI | 8362900/01 | Other | 14-Apr-2026 | - | Resolved | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 2 | Baghpat | LC INFRA | Hasanpur Masoori W/S Scheme | Hasanpur Masoori | 20014070/01 | Other | 08-Dec-2025 | - | Resolved | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 3 | Baghpat | LC INFRA | Meetli Water Supply Scheme | MEETLI | 20057079/01 | Other | 19-Aug-2025 | - | Resolved | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 4 | Baghpat | LC INFRA | KHEDAKI | KHERIKI | 8362902/01 | Other | 03-Aug-2025 | - | Resolved | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 5 | Baghpat | LC INFRA | Vazidpur wss | Vazidpur | 20060344/01 | Other | 23-Jul-2025 | - | Resolved | NOCs from PWD is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |