Construction Schemes Disruptions



S.No. District Agency Scheme Village OHT Code Disruption Type Disruption Date Expected Resolve Date Status Remark
1 Baghpat LC INFRA TAYODHI TYODHI 8362900/01 Other 14-Apr-2026 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
2 Baghpat LC INFRA Hasanpur Masoori W/S Scheme Hasanpur Masoori 20014070/01 Other 08-Dec-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
3 Baghpat LC INFRA Meetli Water Supply Scheme MEETLI 20057079/01 Other 19-Aug-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
4 Baghpat LC INFRA KHEDAKI KHERIKI 8362902/01 Other 03-Aug-2025 - Resolved NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
5 Baghpat LC INFRA Vazidpur wss Vazidpur 20060344/01 Other 23-Jul-2025 - Resolved NOCs from PWD is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
6 Baghpat LC INFRA Pali W/S Scheme PALI 20014196/01 Other 09-Jun-2025 - Pending NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme.
7 Baghpat LC INFRA Nagla Bahlolpur W/S SCHEME Nagla Bahlolpur 20093602/01 Other 18-May-2025 - Pending NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
8 Baghpat LC INFRA SISANA SISANA 8363897/01 Other 12-May-2025 - Pending NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
9 Baghpat LC INFRA mahavatpur Mahavatpur 20014269/01 Other 12-May-2025 - Pending NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
10 Baghpat LC INFRA Abdullapur W/S Scheme Abdullapur 20099984/01 Other 01-Mar-2024 - Pending Jail authorities stopped OHT work due to safety norms.