| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | KHIRIA RATAN | Khiria Ratan | 20016531/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 2 | Shahjahanpur | NCC Ltd. | Sikenderpur afganan | Sikenderpur Afgnan | 20018427/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 3 | Shahjahanpur | NCC Ltd. | SIRKHIRI & BHARTAPUR WSS | Bhartapur | 20058392/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 4 | Shahjahanpur | NCC Ltd. | AMANPUR WSS | Amanpur | 20071368/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 5 | Shahjahanpur | NCC Ltd. | CHAUKHUTIA & KAKRALA & ATIWARA WSS | Kakrala | 20073329/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 6 | Shahjahanpur | NCC Ltd. | ABHAIN & BARUA BUZURG MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Abhain | 20084188/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 7 | Shahjahanpur | NCC Ltd. | ATHKONA & RAMPUR KALAN & RAUTAPUR KALAN MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Madhaupur | 20084322/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 8 | Shahjahanpur | NCC Ltd. | KEWAL RAMPUR CHILAUA, KOYALAGYANPUR, RAMPUR MULTI GP WSS | Kewal Rampur Chilaua | 20089062/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 9 | Shahjahanpur | NCC Ltd. | KUTUAPUR ELAQUA SAHERAMAU GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Kutuapur Elaqua Saheramau | 20096533/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 10 | Shahjahanpur | NCC Ltd. | PATNA WSS | Patna | 20078973/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 11 | Shahjahanpur | NCC Ltd. | FIROZPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Vilhara | 20084338/01 | NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL) | 14-Aug-2026 | 30-Jun-2028 | Pending | NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme |
| 12 | Shahjahanpur | NCC Ltd. | DADIURA & NIYAMATPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Dadiura | 20084170/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Oct-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 13 | Shahjahanpur | NCC Ltd. | VIKRAMPUR CHAKAURA Nigohi W/s | Vikrampur Chakaura | 20015058/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 14 | Shahjahanpur | NCC Ltd. | Dhubla Karimnagar | Dhuvla Karimnagar | 20019783/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Jun-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 15 | Shahjahanpur | NCC Ltd. | BENIPUR WSS | Benipur | 20058760/01 | Land Dispute / Litigation | 05-Aug-2026 | 30-Jun-2028 | Pending | Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme. |
| 16 | Shahjahanpur | NCC Ltd. | DOSHPUR THOK GRAM PANCHAYAT WATER SUPPLY SCHEME | Doshpur Thok | 20101596/01 | Saline Water / Poor Water Quality (Salinity/Fluoride/Iron) | 05-Aug-2026 | 30-Jun-2028 | Pending | Tubewell has been drilled once/ twice/thrice, saline water was encountered. Additional land is required for another bore and acquisition of the same is under process therefore. additional time is required for the completion of the scheme |
| 17 | Shahjahanpur | NCC Ltd. | JAITIPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Jaitipur | 8361729/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 18 | Shahjahanpur | NCC Ltd. | VAIDAPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | Paidapur | 20084382/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 30-Jun-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 19 | Shahjahanpur | NCC Ltd. | BEHTI GP MULTI VILLAGE WSS | Behti | 20093768/01 | Land Dispute / Litigation | 05-Aug-2026 | 31-Oct-2028 | Pending | A legal dispute concerning the land for the water works is pending. Therefore, additional time is required for the completion of the scheme. |
| 20 | Shahjahanpur | NCC Ltd. | SITHARA GP MULTI VILLAGE WSS | Sithara | 20093790/01 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Jun-2028 | Pending | Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme. |
| 21 | Shahjahanpur | NCC Ltd. | RAMPUR GP WSS | Rampur | 20099668/01 | Water Logged / Flood-Prone Area / Natural Calamity | 05-Aug-2026 | 31-Oct-2028 | Pending | The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme |
| 22 | Shahjahanpur | NCC Ltd. | MAU VASAK GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | Mau Vasak | 20096496/01 | Land Dispute / Litigation | 05-Aug-2026 | 30-Jun-2028 | Pending | A legal dispute concerning the land for the water works is pending. Therefore, additional time is required for the completion of the scheme. |
| 23 | Shahjahanpur | NCC Ltd. | SHAHVEGNAGAR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | Shahvegpur | 20097898/01 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2027 | Pending | Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme. |