| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | PADRAHI | Dhanha | 8386856-OHT1 | Land Dispute / Litigation | 25-Dec-2025 | 25-Dec-2026 | Pending | Main gate & Approach Road Issue |
| 2 | Kushi Nagar | NCC Ltd. | NAKATAHA BASDILA | Nakataha Basdila | 20097035-OHT1 | Land Dispute / Litigation | 20-Jan-2025 | 26-Sep-2026 | Pending | High court Stay- Water Supply affected. |
| 3 | Kushi Nagar | NCC Ltd. | BELWA | Belwa | 20079931-OHT1 | Road Widening / Pipeline Damage | 21-Dec-2024 | 20-Oct-2026 | Pending | Road wideing -6256 Mtr & 67 Nos FHTC Damaged. |
| 4 | Kushi Nagar | NCC Ltd. | ARNAHAVA | Ahernwa | 20078947-OHT1 | Land Dispute / Litigation | 25-Oct-2024 | 15-Oct-2026 | Pending | land short issue |
| 5 | Kushi Nagar | NCC Ltd. | DEULIA MANIYA CHHAPRA | Deulia Maniya Chhapra | 20072917-OHT1 | Land Dispute / Litigation | 15-Jun-2024 | 20-Oct-2026 | Pending | 11 KV LINE BETWEEN CAMPUS OHT CONST. HEIGHT STOP |
| 6 | Kushi Nagar | NCC Ltd. | MALHO | Tulsi Patti | 8388204-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 20-Nov-2026 | Pending | Electricty Connection not done Yet. |
| 7 | Kushi Nagar | NCC Ltd. | PATHARWA | Patharwa | 20042728-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 20-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 8 | Kushi Nagar | NCC Ltd. | PARASAUNI BUZURG RO | Parasauni Buzurg | 20098932-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 15-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 9 | Kushi Nagar | NCC Ltd. | GANESH PATTI | Ganesh Patti | 20102413-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 20-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 10 | Kushi Nagar | NCC Ltd. | NARCHOCHWA | Nar Chochawa | 20082076-OHT1 | Land Dispute / Litigation | 25-Apr-2024 | 15-Oct-2026 | Pending | ROW in B-wall+ Pipal Tree in Solar area , Villagers are opposing the cutting of Pipal Tree. |
| 11 | Kushi Nagar | NCC Ltd. | PIPRAGHAT | Pipraghat Ahatmali | 20097042-OHT1 | Electricity Connection Pending | 02-Mar-2024 | 15-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 12 | Kushi Nagar | NCC Ltd. | KURMAUL Urf SOHANPUR | Kurmaul Urf Sohanpur | 20098904-OHT1 | Electricity Connection Pending | 16-Feb-2024 | 15-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 13 | Kushi Nagar | NCC Ltd. | PARSA URF SIRSIA | Parsa Ahatmali | 20042706-OHT1 | Electricity Connection Pending | 03-Feb-2024 | 15-Oct-2026 | Pending | Electricty Connection not done Yet. |
| 14 | Kushi Nagar | NCC Ltd. | BARTHA | Bartha | 20097032-OHT1 | Land Dispute / Litigation | 25-Aug-2023 | 31-Oct-2026 | Pending | Full Row/ Court Case |
| 15 | Kushi Nagar | NCC Ltd. | BASDILA KHURD | Basdila Khurd | 8388200-OHT1 | Land Dispute / Litigation | 04-Apr-2022 | 24-Oct-2026 | Pending | Full ROW/ Court Case |