Pending Construction Schemes Disruptions



S.No. District Agency Scheme Village OHT Code Disruption Type Disruption Date Expected Resolve Date Status Remark
1 Kushi Nagar NCC Ltd. PADRAHI Dhanha 8386856-OHT1 Land Dispute / Litigation 25-Dec-2025 25-Dec-2026 Pending Main gate & Approach Road Issue
2 Kushi Nagar NCC Ltd. NAKATAHA BASDILA Nakataha Basdila 20097035-OHT1 Land Dispute / Litigation 20-Jan-2025 26-Sep-2026 Pending High court Stay- Water Supply affected.
3 Kushi Nagar NCC Ltd. BELWA Belwa 20079931-OHT1 Road Widening / Pipeline Damage 21-Dec-2024 20-Oct-2026 Pending Road wideing -6256 Mtr & 67 Nos FHTC Damaged.
4 Kushi Nagar NCC Ltd. ARNAHAVA Ahernwa 20078947-OHT1 Land Dispute / Litigation 25-Oct-2024 15-Oct-2026 Pending land short issue
5 Kushi Nagar NCC Ltd. DEULIA MANIYA CHHAPRA Deulia Maniya Chhapra 20072917-OHT1 Land Dispute / Litigation 15-Jun-2024 20-Oct-2026 Pending 11 KV LINE BETWEEN CAMPUS OHT CONST. HEIGHT STOP
6 Kushi Nagar NCC Ltd. MALHO Tulsi Patti 8388204-OHT1 Electricity Connection Pending 04-Jun-2024 20-Nov-2026 Pending Electricty Connection not done Yet.
7 Kushi Nagar NCC Ltd. PATHARWA Patharwa 20042728-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Pending Electricty Connection not done Yet.
8 Kushi Nagar NCC Ltd. PARASAUNI BUZURG RO Parasauni Buzurg 20098932-OHT1 Electricity Connection Pending 04-Jun-2024 15-Oct-2026 Pending Electricty Connection not done Yet.
9 Kushi Nagar NCC Ltd. GANESH PATTI Ganesh Patti 20102413-OHT1 Electricity Connection Pending 04-Jun-2024 20-Oct-2026 Pending Electricty Connection not done Yet.
10 Kushi Nagar NCC Ltd. NARCHOCHWA Nar Chochawa 20082076-OHT1 Land Dispute / Litigation 25-Apr-2024 15-Oct-2026 Pending ROW in B-wall+ Pipal Tree in Solar area , Villagers are opposing the cutting of Pipal Tree.
11 Kushi Nagar NCC Ltd. PIPRAGHAT Pipraghat Ahatmali 20097042-OHT1 Electricity Connection Pending 02-Mar-2024 15-Oct-2026 Pending Electricty Connection not done Yet.
12 Kushi Nagar NCC Ltd. KURMAUL Urf SOHANPUR Kurmaul Urf Sohanpur 20098904-OHT1 Electricity Connection Pending 16-Feb-2024 15-Oct-2026 Pending Electricty Connection not done Yet.
13 Kushi Nagar NCC Ltd. PARSA URF SIRSIA Parsa Ahatmali 20042706-OHT1 Electricity Connection Pending 03-Feb-2024 15-Oct-2026 Pending Electricty Connection not done Yet.
14 Kushi Nagar NCC Ltd. BARTHA Bartha 20097032-OHT1 Land Dispute / Litigation 25-Aug-2023 31-Oct-2026 Pending Full Row/ Court Case
15 Kushi Nagar NCC Ltd. BASDILA KHURD Basdila Khurd 8388200-OHT1 Land Dispute / Litigation 04-Apr-2022 24-Oct-2026 Pending Full ROW/ Court Case