Total Visitors April 2023 - Till Date
| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON | Kasauna Khurd GP WSS | KASAUNA KHURD | 20084486/01 | Public Hindrance / Local Hindrance | 03-Jun-2023 | - | Resolved | yahan kafi lambe samay se alloted land par local public ka hinrance hai, kyonki ye SVS hai to yahan kary complete karne ka samay bhi bahut kam hai |
| 2 | Sant Kabeer Nagar | VISHVARAJ | Sais Rao Mafi GP WSS | Sahs Rauwa Maphi | 20087676 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | The construction work could not be commenced due to encroachment on the village government approach road. However, the tube well has been constructed. |
| 3 | Sant Kabeer Nagar | VISHVARAJ | SIYARA SANTHA GP WSS | Siyara Santha | 20085970 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | No approach road is available to the government land for construction activities. Although the tube well has been constructed, the remaining works could not be started due to the lack of an approach road. |
| 4 | Sant Kabeer Nagar | VISHVARAJ | TEJPUR GP WSS | Tejpur | 20090056 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | No approach road is available to the government land for construction activities. Although the tube well has been constructed, the remaining works could not be started due to the lack of an approach road. |
| 5 | Sant Kabeer Nagar | VISHVARAJ | BACHCHAIPUR GP WSS | Bachhaipur | 20086341 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | The tube well has been constructed; however, the remaining works could not be commenced due to the lack of a suitable approach road. |
| 6 | Sant Kabeer Nagar | VISHVARAJ | PADARAI WATER SUPPLY SCHEME | Paraisya | 20093169 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | No approach road is available to the government land for carrying out the construction work. The village is under the land consolidation (Chakbandi) process. The tube well has been constructed; however, the remaining works could not be commenced due to the absence of an approach road. |
| 7 | Sant Kabeer Nagar | VISHVARAJ | BANTWAR & BELMA GOV WATER SUPPLY SCHEME | Bantwar | 20094318 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Belma village are demanding a separate overhead water tank, due to which they are obstructing the pipeline laying and household connection works. |
| 8 | Sant Kabeer Nagar | VISHVARAJ | RAJNAULI & SANTHI GP WSS | Rajnauli | 20086765 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Rajnauli village are demanding a separate overhead water tank, resulting in resistance to the pipeline laying and household connection works. |
| 9 | Sant Kabeer Nagar | VISHVARAJ | DARUA JAPTI ADALAT & SHIVAPAR GOV WSS | Darua Japti Adalat | 20086124 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land for construction activities. The tube well has been constructed; however, the remaining works could not be carried out without obstruction due to the absence of an approach road. |
| 10 | Sant Kabeer Nagar | VISHVARAJ | ASHRAFABAD, MOHAMMADPUR & MOHIUDDINPUR GOV W/S Scheme | Asharfabad | 20094214 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | No approach road is available to the government land at the 2nd land location for carrying out the construction work. Consequently, the construction work is being hindered. |
| 11 | Sant Kabeer Nagar | VISHVARAJ | TENUHARI DOEM | Tenuhari Doem | 20085422 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 18-Nov-2026 | Pending | No approach road is available to the government land. Due to the absence of an approach road, the remaining works could not be commenced. |
| 12 | Sant Kabeer Nagar | VISHVARAJ | GANGAICHA & JATEDEEHA GOV WSS | Jatedeeha Dubaulia | 20086874 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Oct-2026 | Pending | The villagers are opposing the use of the private approach road, which is hindering the construction work. |
| 13 | Sant Kabeer Nagar | VISHVARAJ | Sehura & Koelsa GOV WSS | Sehura | 20086908 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land. Consequently, the construction work cannot be executed smoothly due to the absence of an approach road. |
| 14 | Sant Kabeer Nagar | VISHVARAJ | Pipra Doman & Muradeeha Khurd GP WSS | Pipra Doman | 20086895 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Dec-2026 | Pending | No approach road is available to the government land. |
| 15 | Sant Kabeer Nagar | VISHVARAJ | CHAGERA MANGERA GP WSS | Chagera Mangera | 20085382 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The pipeline from Tube Well-2 to the Overhead Tank (OHT) campus could not be laid due to issues related to the availability of an approach route. |