| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hathras | BGCCPL-Ramky (JV) | CHANDAPA WATER SUPPLY SCHEME | Chandapa | 20087480/01 | Land Dispute / Litigation | 13-Mar-2026 | - | Resolved | Approach road issue |
| 2 | Hathras | BGCCPL-Ramky (JV) | DHANDAULI WSS | Dhandholi | 20071579/01 | Electricity Connection Pending | 06-Feb-2026 | 03-Sep-2026 | Resolved | Dhandauli TW payment done on 06.02.2026. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month |
| 3 | Hathras | BGCCPL-Ramky (JV) | ALHEPUR TURSEN | Alhepur Tursen | 20073954/01 | Other | 28-Dec-2025 | - | Resolved | Approch Road Not available |
| 4 | Hathras | BGCCPL-Ramky (JV) | NAGLA KHARGU WSS | Nagla Kharag | 20069102/01 | Other | 19-Dec-2025 | - | Resolved | Approch Road Not available |
| 5 | Hathras | BGCCPL-Ramky (JV) | MITANPUR WATER SUPPLY SCHEME | Mitanpur | 20087362/01 | Land Not Available / Short Land | 12-Nov-2025 | - | Resolved | Insufficient land for construction work. |
| 6 | Hathras | BGCCPL-Ramky (JV) | PAHARPUR WSS | Paharpur | 20072464/01 | Land Not Available / Short Land | 16-Oct-2025 | - | Resolved | Insufficient land for construction work. |
| 7 | Hathras | BGCCPL-Ramky (JV) | MITANPUR WATER SUPPLY SCHEME | Bhogaon Nagla Jayas | 20087362/01 | Electricity Connection Pending | 17-Sep-2024 | 03-Sep-2026 | Resolved | Mitanpur TW payment done on 17.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month |
| 8 | Hathras | BGCCPL-Ramky (JV) | DAUDA BANKA WATER SUPPLY SCHEME | DAUDA | 20098369/01 | Public Hindrance / Local Hindrance | 16-Sep-2024 | - | Resolved | electric Connection still Pending |
| 9 | Hathras | BGCCPL-Ramky (JV) | KARAIYA WATER SUPPLY SCHEME | Karaiya | 20061070/01 | Electricity Connection Pending | 16-Sep-2024 | 03-Sep-2026 | Resolved | Karaiya TW payment done on 16.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month |
| 10 | Hathras | BGCCPL-Ramky (JV) | DHANOTI WATER SUPPLY SCHEME | Dhanothi | 20098363/01 | Electricity Connection Pending | 17-Aug-2024 | 03-Sep-2026 | Resolved | Dhanoti TW payment done on 17.08.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month |
| 11 | Hathras | BGCCPL-Ramky (JV) | TONDA WATER SUPPLY SCHEME | Tonda | 20092744/01 | Electricity Connection Pending | 14-Mar-2024 | - | Resolved | Tonda TW payment done on 14.03.2024. Connection still pending |
| 12 | Hathras | ION EXCHANGE | RASGAWAN WSS | Chamarpur | ZONE03 | Electricity Connection Pending | 04-Aug-2026 | 15-Sep-2026 | Resolved | Electric estimation was paid on 6/09/2024. Connection still pending |
| 13 | Hathras | ION EXCHANGE | SHEIKHUPUR AJIT WSS | Tataarpur | ZONE04 | Electricity Connection Pending | 04-Aug-2026 | 15-Sep-2026 | Resolved | Connection payment was done on 27.06.2023. Connection still pending |
| 14 | Hathras | ION EXCHANGE | RASGAWAN WSS | Kheria | ZONE04 | Electricity Connection Pending | 04-Aug-2026 | 15-Sep-2026 | Resolved | Connection payment was done on 16.02.2024. Connection still pending |
| 15 | Hathras | ION EXCHANGE | SALEMPUR WSS | Madhapithu | ZONE02 | Electricity Connection Pending | 04-Aug-2026 | 15-Sep-2026 | Resolved | For Borewell No 1 connection was paid on 19.12.2023. Connection still pending |
| 16 | Hathras | ION EXCHANGE | TASINGA WSS | Tasinga | ZONE01 | Electricity Connection Pending | 04-Aug-2026 | 20-Sep-2026 | Resolved | Tasinga BW 1 payment done on 21.08.2021. Connection still pending |
| 17 | Hathras | ION EXCHANGE | TASINGA WSS | Tasinga | ZONE01 | Electricity Connection Pending | 04-Aug-2026 | 16-Sep-2026 | Resolved | Tasinga TW 2 connection payment was done on 21.08.2024. Connection still pending |
| 18 | Hathras | ION EXCHANGE | TASINGA WSS | Tasinga | ZONE01 | Electricity Connection Pending | 04-Aug-2026 | 17-Sep-2026 | Resolved | Tasinga TW 3 connection payment was done on 06.09.2024. Connection still pending |