| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON | Aurahi GP WSS | Aurahi | 20085113/01 | Road Widening / Pipeline Damage | 31-Jul-2024 | - | Resolved | is scheme me mukhy sadak ke sath rahne vale gharon ke supplybadhitb hai yahan se jane wali mukhy sadak me dali gai HDPE pipe lagbhag 450 meter road wedining ke karan damage ho gai hai or sanda me pani nahin ja pa rha hai |
| 2 | Sant Kabeer Nagar | JAKSON | Aurahi Gram Panchayat Water Supply Scheme | Aurahi | 20094493/01 | Land Not Available / Short Land | 03-Jun-2024 | - | Resolved | yahan allotted land NH me aane ke karan bore hone ke bad koi kary nahin ho paya hai or ab nai land allot nahin ho paa rahi hai jiske karan yahan kary badhit hai |
| 3 | Sant Kabeer Nagar | JAKSON | Chharachh GRAM PANCHAYAT WATER SUPPLY SCHEME | Chharach | 20094109/01 | Land Not Available / Short Land | 06-Sep-2023 | - | Resolved | shuru se hi yahan koi land nahin mil pa rahi hai isliye yahan kary shuru nahin ho paya hai |
| 4 | Sant Kabeer Nagar | JAKSON | Kasauna Khurd GP WSS | KASAUNA KHURD | 20084486/01 | Public Hindrance / Local Hindrance | 03-Jun-2023 | - | Resolved | yahan kafi lambe samay se alloted land par local public ka hinrance hai, kyonki ye SVS hai to yahan kary complete karne ka samay bhi bahut kam hai |
| 5 | Sant Kabeer Nagar | VISHVARAJ | BANTWAR & BELMA GOV WATER SUPPLY SCHEME | Bantwar | 20094318 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Belma village are demanding a separate overhead water tank, due to which they are obstructing the pipeline laying and household connection works. |
| 6 | Sant Kabeer Nagar | VISHVARAJ | RAJNAULI & SANTHI GP WSS | Rajnauli | 20086765 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Rajnauli village are demanding a separate overhead water tank, resulting in resistance to the pipeline laying and household connection works. |
| 7 | Sant Kabeer Nagar | VISHVARAJ | GARH SARPAR | Garh Sardar | 20084983 | Other | 05-Aug-2026 | 31-Dec-2026 | Resolved | A 132 kV transmission line passes adjacent to the project campus, and the concerned Electricity Department has instructed that no construction work be carried out in the area. The work is to be executed after preparing a suitable work plan under the guidance of the Executive Engineer. |
| 8 | Sant Kabeer Nagar | VISHVARAJ | DARUA JAPTI ADALAT & SHIVAPAR GOV WSS | Darua Japti Adalat | 20086124 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land for construction activities. The tube well has been constructed; however, the remaining works could not be carried out without obstruction due to the absence of an approach road. |
| 9 | Sant Kabeer Nagar | VISHVARAJ | Dhauripar Barhya GP WSS | Dhauripar Parhya | 20085876 | Land Not Available / Short Land | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land, due to which the construction work is being hindered. The issue needs to be resolved after conducting a land survey and demarcation. |
| 10 | Sant Kabeer Nagar | VISHVARAJ | Sehura & Koelsa GOV WSS | Sehura | 20086908 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land. Consequently, the construction work cannot be executed smoothly due to the absence of an approach road. |
| 11 | Sant Kabeer Nagar | VISHVARAJ | PURAINA ,& RUDHAULI GOV WSS | Puraina | 20085370 | Land Dispute / Litigation | 05-Aug-2026 | 30-Nov-2026 | Resolved | The villagers are disputing the provision of an approach road. Consequently, the construction work cannot be carried out without obstruction due to the unavailability of an approach road. |
| 12 | Sant Kabeer Nagar | VISHVARAJ | CHAGERA MANGERA GP WSS | Chagera Mangera | 20085382 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The pipeline from Tube Well-2 to the Overhead Tank (OHT) campus could not be laid due to issues related to the availability of an approach route. |