| 1 | Kushi Nagar | NCC Ltd. | KHESIA RO | Khesia | 20098902-OHT1 | Road Widening / Pipeline Damage | 04-Aug-2026 | - | Resolved | Approx 250 Mtr Pipe line Damaged due to Road widening issue. |
| 2 | Kushi Nagar | NCC Ltd. | RAHASU KHUDRA GROUP OF G.PS | Rahasu | 20074588-OHT1 | Road Widening / Pipeline Damage | 04-Aug-2026 | - | Resolved | Approx 200 mtr Pipe line has been damaged due to Road widening issue. |
| 3 | Kushi Nagar | NCC Ltd. | NEBUA RAI GANJ | Nebua Rai Ganj | 20078350-OHT1 | Road Widening / Pipeline Damage | 20-Mar-2026 | 20-Sep-2026 | Resolved | Approx 4025 Mtr Pipe line has been Damaged.Due to Road widening. |
| 4 | Kushi Nagar | NCC Ltd. | RAMPUR BUZURG | Rampur Buzurg | 20082197-OHT1 | Road Widening / Pipeline Damage | 19-Mar-2026 | 15-Oct-2026 | Resolved | 2393 Mtr Pipe Line Damaged & 59 FHTC Nos |
| 5 | Kushi Nagar | NCC Ltd. | MUNDERA UPADHYA GOGP | Karmahi | 20078343-OHT1 | Road Widening / Pipeline Damage | 13-Mar-2026 | 15-Oct-2026 | Resolved | 1791 Mtr Pipe line Damaged & 33 Nos FHTC Damaged. |
| 6 | Kushi Nagar | NCC Ltd. | MUNDERA UPADHYA GOGP | MUNDERA | 20078343-OHT1 | Road Widening / Pipeline Damage | 10-Mar-2026 | 20-Feb-2027 | Resolved | Approx 1791 Mtr Pipe line has been damaged due Road widening. |
| 7 | Kushi Nagar | NCC Ltd. | PIPRAWAR SIWAN | Piprawar Siwan | 20078694-OHT1 | Road Widening / Pipeline Damage | 04-Mar-2026 | 20-Oct-2026 | Resolved | Approx 1678 Mtr Pipe line has been damaged due to Road widening. |
| 8 | Kushi Nagar | NCC Ltd. | RAMPUR BUZURG | Rampur Buzurg | 20082197-OHT1 | Road Widening / Pipeline Damage | 04-Mar-2026 | 25-Dec-2026 | Resolved | Approx 2393 Mtr Pipe line have been damaged due to Road widening. |
| 9 | Kushi Nagar | NCC Ltd. | RAKBARAJA | Rakbaraja | 8388206-OHT1 | Road Widening / Pipeline Damage | 04-Mar-2026 | 25-Feb-2027 | Resolved | Approx 2809 Mtr Pipe laine damaged due to Road Wideing. |
| 10 | Kushi Nagar | NCC Ltd. | VIJAIPUR | Vijaipur | 20051261-OHT1 | Road Widening / Pipeline Damage | 04-Mar-2026 | 20-Jan-2027 | Resolved | 777 mtr pipe line has been damaged due to Road widening issue. |
| 11 | Kushi Nagar | NCC Ltd. | RAMPUR BHAT | Rampur Bhat | 8388174-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 20-Jan-2027 | Resolved | 723 mtr Pipe line has been damaged due to Road wideing issue. |
| 12 | Kushi Nagar | NCC Ltd. | INDERSENWA | Ramkola | 20097181-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 20-Oct-2026 | Resolved | Approx 691 Mtr Pipe line has been damaged due to Road widening issue. |
| 13 | Kushi Nagar | NCC Ltd. | AHIRAULI DAN | Ahirauli Dan | 20102429-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 04-Nov-2027 | Resolved | Approx 1831 Mtr Pipe line has been damaged |
| 14 | Kushi Nagar | NCC Ltd. | KURMAUTA | Kurmauta | 20097190-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 20-Oct-2026 | Resolved | Approx 2751 Mtr Pipe laying has been Damaged due to Road Widening. |
| 15 | Kushi Nagar | NCC Ltd. | PADRI MEHDIA | Padri Mehdia | 20101619-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 20-Oct-2026 | Resolved | Approx 1489 Mtr Pipe line has been damaged due to Road widening. |
| 16 | Kushi Nagar | NCC Ltd. | SEMARA HARDO | Semara Hardo | 20097025-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | - | Resolved | Approx 200 Mtr Pipe line has been Damaged due to Road wideing issue. |
| 17 | Kushi Nagar | NCC Ltd. | KHAJURI | Khajuri | 8387101-OHT1 | Road Widening / Pipeline Damage | 04-Feb-2026 | 04-Feb-2027 | Resolved | Approx 1176 Mtr Pipe line has been damaged due to Road wideing issue. |
| 18 | Kushi Nagar | NCC Ltd. | PIPRAGHAT | Pipraghat Ahatmali | 20097042-OHT1 | Road Widening / Pipeline Damage | 20-Jan-2026 | 21-Feb-2027 | Resolved | Approx 400 mtr pipe line has been damaged due to Road widening issue. |
| 19 | Kushi Nagar | NCC Ltd. | RAMBAR BUZURG | Rambar Buzurg | 8388196-OHT1 | Road Widening / Pipeline Damage | 20-Jan-2026 | 04-Jan-2027 | Resolved | Approx 341 mtr pipe line has been damaged due to Road wideing issue. |
| 20 | Kushi Nagar | NCC Ltd. | TURK WALIA DARIYAO SINGH | Turk Walia Dariyao Singh | 20078365-OHT1 | Road Widening / Pipeline Damage | 20-Jan-2026 | 20-Jan-2027 | Resolved | Approx 250 mtr Pipe line has been damaged due to Road wideing issue. |
| 21 | Kushi Nagar | NCC Ltd. | ADRAUNA GOGP | Adrauna | 20078925-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 20-Oct-2026 | Resolved | Approx 250 mtr pipe line has been damaged due to Road wideing issue. |
| 22 | Kushi Nagar | NCC Ltd. | CHANDARPUR | Chandarpur | 20082193-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 20-Feb-2027 | Resolved | Approx 637 mtr pipe line has been damaged due to Road wideing issue. |
| 23 | Kushi Nagar | NCC Ltd. | MAGHWALIYA | Madhwalia | 20097046-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 15-Jan-2027 | Resolved | Approx 572 Mtr Pipe line has been damaged due to Road wideing issue. |
| 24 | Kushi Nagar | NCC Ltd. | GULELAHA | Gulelha | 20097026-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 20-Jan-2027 | Resolved | 550 mtr Pipe line has been damaged due to Road widening issue. |
| 25 | Kushi Nagar | NCC Ltd. | JOKVA BUJURG | Jokwa Buzurg | 20077431-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 04-Feb-2027 | Resolved | Approx 525.8 Mtr pipe line has been damaged due to road wideing issue. |
| 26 | Kushi Nagar | NCC Ltd. | RAIPUR KHAS | Rampur Khas | 20081713-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 10-Feb-2027 | Resolved | Approx 1982 Mtr Pipe line has been damaged due to Road widening issue. |
| 27 | Kushi Nagar | NCC Ltd. | MORWAN | Morwan | 20073407-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 10-Mar-2027 | Resolved | Approx 911 Mtr Pipe line has been damaged due to Road wideing issue. |
| 28 | Kushi Nagar | NCC Ltd. | BELWA URF BELWANIA GOGP | Belwa Urf Belwania | 20079948-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 04-Feb-2027 | Resolved | Approx 236 Mtr Pipe line has been damaged due to Road wideinging issue. |
| 29 | Kushi Nagar | NCC Ltd. | GAURI SHRIRAM | Gauri Shri Ram | 20082320-OHT1 | Road Widening / Pipeline Damage | 04-Jan-2026 | 04-Feb-2027 | Resolved | Approx 230 mtr Pipe line has been damaged due to Road wideening issue. |
| 30 | Kushi Nagar | NCC Ltd. | MISRAULI | Misrauli | 8388235-OHT1 | Land Dispute / Litigation | 04-Jan-2026 | 15-Oct-2026 | Resolved | B Wall is under ROW by Villagers & Pradhan |
| 31 | Kushi Nagar | NCC Ltd. | HATA-5 | Hata | 20077208-OHT1 | Road Widening / Pipeline Damage | 25-Dec-2025 | 20-Feb-2027 | Resolved | Approx 3634 Mtr Pipe line have been Damaged due Road widening. |
| 32 | Kushi Nagar | NCC Ltd. | MAHUA | Mahuawa | 20101615-OHT1 | Road Widening / Pipeline Damage | 20-Dec-2025 | 20-Feb-2027 | Resolved | Approx 3895 Mtr Pipe line Damaged due to Road widening. |
| 33 | Kushi Nagar | NCC Ltd. | JUNGLE KHIRKHIA | Jungle Khirkia | 20082127-OHT1 | Road Widening / Pipeline Damage | 20-Dec-2025 | 20-Jan-2027 | Resolved | 831 Mtr Pipe line has been damaged due to Road wideing issue. |
| 34 | Kushi Nagar | NCC Ltd. | SOHASAPATTI GOUSI GOGP | Sohsa Patti Gausi | 20078357-OHT1 | Road Widening / Pipeline Damage | 11-Dec-2025 | 13-Jan-2027 | Resolved | Approx 1269 Mtr Pipe line has been damaged due to road wideing issue. |
| 35 | Kushi Nagar | NCC Ltd. | Rampur Gonha | Rampur Gonha | 20050005-OHT1 | Road Widening / Pipeline Damage | 04-Dec-2025 | 20-Jan-2027 | Resolved | Approx 2119 Mtr Pipe laying has been Damaged due to Road widening issue. |
| 36 | Kushi Nagar | NCC Ltd. | RAJAWATIA | Rajawatia | 8388216-OHT1 | Road Widening / Pipeline Damage | 04-Dec-2025 | 26-Jan-2027 | Resolved | Approx 470 Mtr pipe line has been damaged due to Road wideing issue. |
| 37 | Kushi Nagar | NCC Ltd. | RAHASUJANUBI PATTI R | Rahasujanubi Patti | 20098931-OHT1 | Road Widening / Pipeline Damage | 04-Dec-2025 | 20-Nov-2026 | Resolved | Approx 4268 Mtr Pipe laying is Damaged due to Road widening. |
| 38 | Kushi Nagar | NCC Ltd. | SAGAR GOSAI GROUP OF G.P.s | Sagar Gosai | 20074583-OHT1 | Road Widening / Pipeline Damage | 04-Dec-2025 | 04-Feb-2027 | Resolved | Approx 1357 Mtr Pipe line has been damaged due to Road wideing issue. |
| 39 | Kushi Nagar | NCC Ltd. | BAULIA | Baulia | 20072945-OHT1 | Road Widening / Pipeline Damage | 04-Dec-2025 | 20-Feb-2027 | Resolved | Approx 872 mtr Pipe line has been damaged due to Road wideing issue. |
| 40 | Kushi Nagar | NCC Ltd. | RAMPUR PATTI | Rampur Patti | 20072608-OHT1 | Road Widening / Pipeline Damage | 04-Nov-2025 | 07-Apr-2027 | Resolved | Approx 1898 Mtr Pipe Line has been damaged due to Road widening issue. |
| 41 | Kushi Nagar | NCC Ltd. | BIRWAT KOMWALIA R | Birwat Komwalia | 20098928-OHT1 | Road Widening / Pipeline Damage | 04-Jul-2025 | 20-Feb-2027 | Resolved | Approx 2233 Mtr Pipe line have been damaged due to Road Widening. |
| 42 | Kushi Nagar | NCC Ltd. | BISHUNPURA M GOGP | Bishunpura | 20078413-OHT1 | Road Widening / Pipeline Damage | 04-Jul-2025 | 30-Aug-2026 | Resolved | Approx 1288 Mtr Pipe line has been damaged due to Road wideing. |
| 43 | Kushi Nagar | NCC Ltd. | MATHIYA URF AKATAHA GOGP | Mathiya Urf Akataha | 20078348-OHT1 | Road Widening / Pipeline Damage | 04-Jul-2025 | 25-Nov-2026 | Resolved | Approx 1251 Mtr Pipe line has been damaged to road wideinging issue. |
| 44 | Kushi Nagar | NCC Ltd. | Bharsar Khas | Bharsar Khas | 20040237-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 10-Oct-2026 | Resolved | Electricity Connection Pending Yet. |
| 45 | Kushi Nagar | NCC Ltd. | BADAHARA BABU-K GOGP | Badahara | 20078366-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 10-Sep-2026 | Resolved | Electricity Connection Pending yet. |
| 46 | Kushi Nagar | NCC Ltd. | AMDARIA | Amadaria | 20073033-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 15-Sep-2026 | Resolved | Electricity conection Pending Yet |
| 47 | Kushi Nagar | NCC Ltd. | CHANDARPUR | Chandarpur | 20082193-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 10-Sep-2026 | Resolved | Electricity Connection Pending. |
| 48 | Kushi Nagar | NCC Ltd. | INDERSENWA | Ramkola | 20097181-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 11-Nov-2026 | Resolved | Electricity Connection Pending yet. |
| 49 | Kushi Nagar | NCC Ltd. | SIDHAWE | Sidhawe | 20082263-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 10-Sep-2026 | Resolved | Electricity Connection Pending Yet. |
| 50 | Kushi Nagar | NCC Ltd. | AHIROULI RAJA GOGP | Ahirauli Raja | 20078933-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 51 | Kushi Nagar | NCC Ltd. | CHARGAHA | Chara Gaha | 20078970-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 52 | Kushi Nagar | NCC Ltd. | GAURI SHRIRAM | Gauri Shri Ram | 20082320-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 20-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 53 | Kushi Nagar | NCC Ltd. | GANGAULI GOGP | Gangauli | 20080227-OHT1 | Electricity Connection Pending | 30-Jun-2025 | 10-Nov-2026 | Resolved | Electricty Connection not done Yet. |
| 54 | Kushi Nagar | NCC Ltd. | SAURAHA BUZURG | Saurha Buzurg | 20073432-OHT1 | Electricity Connection Pending | 03-Jun-2025 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 55 | Kushi Nagar | NCC Ltd. | RAMPUR BAGAHA | Rampur Bagaha | 20082305-OHT1 | Electricity Connection Pending | 03-Jun-2025 | 15-Sep-2026 | Resolved | Electricty Connection not done Yet. |
| 56 | Kushi Nagar | NCC Ltd. | AWARAHI KRITPURA | Awarahi Kritpura | 20082087-OHT1 | Electricity Connection Pending | 03-Jun-2025 | 10-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 57 | Kushi Nagar | NCC Ltd. | MORWAN | Morwan | 20073407-OHT1 | Electricity Connection Pending | 03-Jun-2025 | 15-Oct-2026 | Resolved | Electricaity Connection Pending yet. |
| 58 | Kushi Nagar | NCC Ltd. | BINDUAR | Binduar | 20081809-OHT1 | Electricity Connection Pending | 03-Jun-2025 | 15-Sep-2026 | Resolved | Electricity connection Pending yet. |
| 59 | Kushi Nagar | NCC Ltd. | SUBIDHIYA KHURD | Subidhiya Khurd | 20050917-OHT1 | Land Dispute / Litigation | 30-May-2025 | 15-Oct-2026 | Resolved | Approach Road Issue. |
| 60 | Kushi Nagar | NCC Ltd. | PIPARA MUSTQUIL AGARWA | Pipara Mustquil Agarwa | 20042251-OHT1 | Land Dispute / Litigation | 02-May-2025 | 15-Oct-2026 | Resolved | Personal Land in OHT Campus-Row by Villagers |
| 61 | Kushi Nagar | NCC Ltd. | SOHSA MATHIYA | Sohsa Mathiya | 8362251-OHT1 | Road Widening / Pipeline Damage | 28-Apr-2025 | 15-Oct-2026 | Resolved | 1757 Mtr Pipe Line Damaged & 35 Nos FHTC Damaged. |
| 62 | Kushi Nagar | NCC Ltd. | SOHASAPATTI GOUSI GOGP | Sohsa Patti Gausi | 20078357-OHT1 | Road Widening / Pipeline Damage | 28-Apr-2025 | 15-Oct-2026 | Resolved | 1269 Mtr Pipe line Damaged & 9 Nos FHTC Damaged. |
| 63 | Kushi Nagar | NCC Ltd. | TIKARI GOGP | Tikari | 20078362-OHT1 | Road Widening / Pipeline Damage | 05-Apr-2025 | 15-Oct-2026 | Resolved | 1678 MTR Pipe line Damaged & 18 NOs FHTC Damaged. |
| 64 | Kushi Nagar | NCC Ltd. | KURMAUTA | Kurmauta | 20097190-OHT1 | Road Widening / Pipeline Damage | 19-Feb-2025 | 15-Oct-2026 | Resolved | 2751 Mtr Pipe Line Damaged & 62 Nos FHTC Damaged. |
| 65 | Kushi Nagar | NCC Ltd. | BARWA CHHATARDAS GOGP | Barwa Chhatardas | 20079893-OHT1 | Road Widening / Pipeline Damage | 19-Feb-2025 | 15-Oct-2026 | Resolved | 66 Mtr Pipe line Damaged & 6 Nos FHTC Connection |
| 66 | Kushi Nagar | NCC Ltd. | PACHAR | Pachar | 20101915-OHT1 | Road Widening / Pipeline Damage | 16-Dec-2024 | 15-Oct-2026 | Resolved | 1764 Mtr Pipe line Damaged & 20 Nos FHTC Damaged. |
| 67 | Kushi Nagar | NCC Ltd. | POKHAR BHINDA | Pokhar Bhinda | 20101611-OHT1 | Electricity Connection Pending | 16-Dec-2024 | 10-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 68 | Kushi Nagar | NCC Ltd. | SUGAHI (DHARAMPUR KHURD) | Sugahi | 20078899-OHT1 | Land Dispute / Litigation | 28-Nov-2024 | 25-Sep-2026 | Resolved | OHT, Boundary wall & Solar area is under ROW, Present land is not enough-Villagers |
| 69 | Kushi Nagar | NCC Ltd. | PARORAHA | Paroraha | 20101608-OHT1 | Land Dispute / Litigation | 23-Oct-2024 | 15-Oct-2026 | Resolved | approach Road Issue |
| 70 | Kushi Nagar | NCC Ltd. | NAKATAHA BASDILA | Nakataha Basdila | 20097035-OHT1 | Electricity Connection Pending | 04-Oct-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 71 | Kushi Nagar | NCC Ltd. | GAMBHIRPUR GOGP | Gamhirpur | 20080225-OHT1 | Road Widening / Pipeline Damage | 12-Aug-2024 | - | Resolved | 1538 Mtr Pipe Line Damaged & 45 Nos FHTC Damaged. |
| 72 | Kushi Nagar | NCC Ltd. | PARSAUNA KHURD GOGP | Parsauna Khurd | 20078633-OHT1 | Land Dispute / Litigation | 23-Jul-2024 | 25-Sep-2026 | Resolved | ROW in Approach road towards OHT Campus(CAMPUS JANE KE LIYE ROAD NAHI HA) |
| 73 | Kushi Nagar | NCC Ltd. | JUNGLE KHIRKHIA | Jungle Khirkia | 20082127-OHT1 | Road Widening / Pipeline Damage | 22-Jul-2024 | 15-Oct-2026 | Resolved | 831 Mtr Pipe line Damaged . |
| 74 | Kushi Nagar | NCC Ltd. | SIKTA GOGP | Pipraicha | 20078358-OHT1 | Public Hindrance / Local Hindrance | 04-Jul-2024 | 20-Oct-2026 | Resolved | 3500 Mtr GOGP Issue by Local villagers.Not allowing to work in this Revenue Village. |
| 75 | Kushi Nagar | NCC Ltd. | Rampur Gonha | Rampur Gonha | 20050005-OHT1 | Public Hindrance / Local Hindrance | 15-Jun-2024 | 25-Nov-2026 | Resolved | Parlallel along Railway Line & Pradhan Issue.2360 Mtr Pipe Laying affected. |
| 76 | Kushi Nagar | NCC Ltd. | SARISWA | Khiriya | 20078851-OHT1 | Public Hindrance / Local Hindrance | 10-Jun-2024 | 10-Oct-2026 | Resolved | Due to GOGP Issue 7000 mtr Pipe laying work stopped by Local Villagers. |
| 77 | Kushi Nagar | NCC Ltd. | BARWA RATANPURA RO | Barwa Ratanpur | 20098935-OHT1 | Public Hindrance / Local Hindrance | 04-Jun-2024 | 15-Oct-2026 | Resolved | Local Hindarance up to 3400 Mtr by Local Villagers. |
| 78 | Kushi Nagar | NCC Ltd. | SOHASAPATTI GOUSI GOGP | Sohsa Patti Gausi | 20078357-OHT1 | Public Hindrance / Local Hindrance | 04-Jun-2024 | 20-Oct-2026 | Resolved | Gram pradhan row by Local Hindrance 1920 Mtr |
| 79 | Kushi Nagar | NCC Ltd. | SINGAHA | Sigha | 20101604-OHT1 | Public Hindrance / Local Hindrance | 04-Jun-2024 | 20-Nov-2026 | Resolved | Loacal Hindarance Pipe laying 4104 Mtr .Pipe line laying stop by local villagers. |
| 80 | Kushi Nagar | NCC Ltd. | AHIRAULI | Ahiraule | 20106859-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 81 | Kushi Nagar | NCC Ltd. | KATAURA | Kataura | 20101609-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 10-Nov-2026 | Resolved | Electricity connection not done yet. |
| 82 | Kushi Nagar | NCC Ltd. | MATHIA MAFI RO | Mathiamafi Urf Dukhi Ganeshpur | 20102430-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 20-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 83 | Kushi Nagar | NCC Ltd. | GAURI SHUKUL | Gauri Sukul | 20102417-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 20-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 84 | Kushi Nagar | NCC Ltd. | KHAIRATIYA | Jalal Chhapra | 20106713-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 30-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 85 | Kushi Nagar | NCC Ltd. | RAKBAJUNGLI PATTI R | Rakbajunglli Patti | 20098913-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 86 | Kushi Nagar | NCC Ltd. | BHIURA | BHIURA | 20106858-OHT1 | Electricity Connection Pending | 04-Jun-2024 | 16-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 87 | Kushi Nagar | NCC Ltd. | MITHHA MAFI | MITHHA MAFI | 20042197-OHT1 | Public Hindrance / Local Hindrance | 04-Jun-2024 | 25-Sep-2026 | Resolved | GOGP Issue approx 4030 Mtr .Villagers not allowing Pipe laying Work. |
| 88 | Kushi Nagar | NCC Ltd. | DHARAMPUR PARWAT | Dharampur Khurd | 20040297-OHT1 | Road Widening / Pipeline Damage | 01-May-2024 | 15-Sep-2026 | Resolved | 3064 Mtr Pipe line Damaged by PWD Dept |
| 89 | Kushi Nagar | NCC Ltd. | SAPAHA | Sapaha | 20073383-OHT1 | Land Dispute / Litigation | 25-Apr-2024 | 20-Oct-2026 | Resolved | ROW in Approach road towards OHT Campus(CAMPUS JANE KE LIYE ROAD NAHI HA) |
| 90 | Kushi Nagar | NCC Ltd. | PATERHA | Paterha | 20102431-OHT1 | Electricity Connection Pending | 06-Apr-2024 | 10-Sep-2026 | Resolved | Electricity connection pending yet |
| 91 | Kushi Nagar | NCC Ltd. | MAHUA DIH LAUNGRAPUR GOGP | Baidauli Mahua Dih | 20078331-OHT1 | Public Hindrance / Local Hindrance | 04-Apr-2024 | 20-Oct-2026 | Resolved | GOGP Issue of 10147 Mtr.Pipe laying not done due GOGP Issue by Local Villagers |
| 92 | Kushi Nagar | NCC Ltd. | BASHIA BANBIRPUR | Bashia Banbirpur | 20082134-OHT1 | Land Dispute / Litigation | 21-Feb-2024 | 12-Aug-2026 | Resolved | A Hutment at OHT location, ROW by Villagers |
| 93 | Kushi Nagar | NCC Ltd. | BRINDABAN | Brindaban | 20040280-OHT1 | Electricity Connection Pending | 20-Feb-2024 | 15-Sep-2026 | Resolved | Electrical Connection Pending |
| 94 | Kushi Nagar | NCC Ltd. | GANGRAI | Gangrai | 20102428-OHT1 | Electricity Connection Pending | 20-Feb-2024 | 15-Sep-2026 | Resolved | Electricty Connection not done Yet. |
| 95 | Kushi Nagar | NCC Ltd. | VIJAIPUR | Vijaipur | 20051261-OHT1 | Electricity Connection Pending | 20-Feb-2024 | 10-Oct-2026 | Resolved | electricity connection pending yet. |
| 96 | Kushi Nagar | NCC Ltd. | PAKRI BRIJLAL | Pakari Brijlal No.2 | 8386824-OHT1 | Electricity Connection Pending | 20-Feb-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 97 | Kushi Nagar | NCC Ltd. | SISWA GOPAL | Siswa Gopal | 20050914-OHT1 | Electricity Connection Pending | 20-Feb-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 98 | Kushi Nagar | NCC Ltd. | PADRI MEHDIA | Padri Mehdia | 20101619-OHT1 | Electricity Connection Pending | 16-Feb-2024 | 25-Sep-2026 | Resolved | Electricty Connection not done Yet. |
| 99 | Kushi Nagar | NCC Ltd. | KUCHAYA RO | KUCHAYA | 20098937-OHT1 | Electricity Connection Pending | 16-Feb-2024 | 10-Sep-2026 | Resolved | Electricty Connection not done Yet. |
| 100 | Kushi Nagar | NCC Ltd. | RAHASUJANUBI PATTI R | Rahasujanubi Patti | 20098931-OHT1 | Electricity Connection Pending | 16-Feb-2024 | 15-Sep-2026 | Resolved | Electricty Connection not done Yet. |
| 101 | Kushi Nagar | NCC Ltd. | LALIPAR GOGP | Chhitauni | 20078318-OHT1 | Public Hindrance / Local Hindrance | 10-Feb-2024 | 15-Oct-2026 | Resolved | Local Hindarnce by 1660 Mtr .Pipe |
| 102 | Kushi Nagar | NCC Ltd. | MAHUI KHURD | Bharwalia | 20081810-OHT1 | Public Hindrance / Local Hindrance | 05-Feb-2024 | 20-Nov-2026 | Resolved | GOGP Issue of 4840 Mtr by Local Villagers. |
| 103 | Kushi Nagar | NCC Ltd. | NATWALIYA GOGP | Chirgoda | 20076106-OHT1 | Public Hindrance / Local Hindrance | 04-Feb-2024 | 15-Oct-2026 | Resolved | GOGP Issue of 7209 Mtr by Local Villagers. |
| 104 | Kushi Nagar | NCC Ltd. | KHOTAHI | Khotahi | 20101616-OHT1 | Public Hindrance / Local Hindrance | 04-Feb-2024 | 15-Oct-2026 | Resolved | Local Hinadance 4100 mtr by Villager Stop work. |
| 105 | Kushi Nagar | NCC Ltd. | PIPRAGHAT MUSTKIL R | Pipraghat Mustkil | 20098907/01 | Public Hindrance / Local Hindrance | 04-Feb-2024 | 25-Sep-2026 | Resolved | Gram Pradhan issue by 2000 mtr Pipe laying work stopped. |
| 106 | Kushi Nagar | NCC Ltd. | SANERAMAL CHHAPARA | Pakari Bangar | 20081552-OHT1 | Public Hindrance / Local Hindrance | 04-Feb-2024 | 15-Sep-2026 | Resolved | GOGP issue by Local Villagers approx 5000 Mtr Row by Local Villagers. |
| 107 | Kushi Nagar | NCC Ltd. | PAREWATER GOGP | Bhathahi Raja | 20078353-OHT1 | Public Hindrance / Local Hindrance | 04-Feb-2024 | 10-Oct-2026 | Resolved | GOGP issue by Local Villagers approx 3050 Mtr Pipe laying work stopped by Villagers. |
| 108 | Kushi Nagar | NCC Ltd. | BIRWAT KOMWALIA R | Birwat Komwalia | 20098928-OHT1 | Electricity Connection Pending | 03-Feb-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 109 | Kushi Nagar | NCC Ltd. | CHAKIA SOBHMAL | Chakia | 8388387-OHT1 | Electricity Connection Pending | 03-Feb-2024 | 15-Oct-2026 | Resolved | Electricty Connection not done Yet. |
| 110 | Kushi Nagar | NCC Ltd. | PARSADPUR | Parsadpur | 20101605-OHT1 | Electricity Connection Pending | 03-Feb-2024 | 10-Nov-2026 | Resolved | Electricty Connection not done Yet. |
| 111 | Kushi Nagar | NCC Ltd. | BIJAIPUR UTTAR PATTI | Bijaipur Uttar Patti | 20040274-OHT1 | Land Dispute / Litigation | 14-Jan-2024 | 30-Nov-2026 | Resolved | Pump house is ready at available land, now no land available for OHT & Solar , need some more land in adjacent land on exchange-Local Person, Land owner stoppted the work |
| 112 | Kushi Nagar | NCC Ltd. | MAHUI KHURD | Mahui Khurd | 20081810-OHT1 | Land Dispute / Litigation | 04-Jan-2024 | 30-Sep-2026 | Resolved | Full ROW by Villagers |
| 113 | Kushi Nagar | NCC Ltd. | Baghparna | Motipur | 20039737-OHT1 | Public Hindrance / Local Hindrance | 04-Jan-2024 | 20-Sep-2026 | Resolved | GOGP issue by Local Villagers approx 3010 mtr Pipe laying work stopped by villgers |
| 114 | Kushi Nagar | NCC Ltd. | NARKU CHHAPRA | Narku Chhapra | 20076936-OHT1 | Land Dispute / Litigation | 27-Dec-2023 | 30-Aug-2026 | Resolved | Full Row-by Villagers |
| 115 | Kushi Nagar | NCC Ltd. | AMVA SRI DUBEY | AMWA SRI BUBEY | 20071965-OHT1 | Land Dispute / Litigation | 26-Dec-2023 | 18-Nov-2026 | Resolved | Court stay |
| 116 | Kushi Nagar | NCC Ltd. | RAMPUR BHAT | Rampur Bhat | 8388174-OHT1 | Land Dispute / Litigation | 24-Dec-2023 | 28-Nov-2026 | Resolved | Boundary wall 20 mtr-Row by Villagers |
| 117 | Kushi Nagar | NCC Ltd. | BATAR DERA | Batar Dera | 20079924-OHT1 | Land Dispute / Litigation | 16-Dec-2023 | 24-Sep-2026 | Resolved | 3 sides Boundary wall is in ROW-Pradhan & Villagers |
| 118 | Kushi Nagar | NCC Ltd. | JOGIA SHAMLI PATTI GROUP OF G.P.s | Jogia Hichharai | 20077419-OHT1 | Public Hindrance / Local Hindrance | 04-Jul-2023 | 20-Oct-2026 | Resolved | GOGP Issue in Jogia Hichharai .Pipe laying 7890 Mtr work stopped . |
| 119 | Kushi Nagar | NCC Ltd. | HARAIYA BUZURG | Kohra | 20079384-OHT1 | Public Hindrance / Local Hindrance | 04-Jun-2023 | 15-Sep-2026 | Resolved | GOGP Issue by Villagers approx 4000 Mtr Pipe laying work Stopped by Villagers |