| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Indian Hume Pipe | Karri single village PWS | Karri | 20026084/01 | Road Widening / Pipeline Damage | 04-Aug-2026 | - | Pending | Pipeline Damage by PWD Department. |
| 2 | Etawah | Indian Hume Pipe | Bholi | Bholi | 20015755/01 | Road Widening / Pipeline Damage | 04-Aug-2026 | - | Pending | Pipeline Damage by NHAI Department. |
| 3 | Etawah | OMIL-JWIL (JV) | BAHARPUR | Baharpur | 20092960/01 | Road Widening / Pipeline Damage | 05-Jun-2026 | 04-Sep-2026 | Resolved | Road widening issue |
| 4 | Etawah | OMIL-JWIL (JV) | LAHROI | Lahroi | 20064378/01 | Road Widening / Pipeline Damage | 05-May-2026 | 30-Nov-2026 | Resolved | Road widening work was started by temprorily no work is noging. |