Construction Schemes Disruptions



S.No. District Agency Scheme Village OHT Code Disruption Type Disruption Date Expected Resolve Date Status Remark
1 Etah ION EXCHANGE Nagla Sukhdev Gram Panchayat Re-Organization W/S Scheme Nagla Sukhdev ZONE01 Electricity Connection Pending 03-Aug-2026 15-Sep-2026 Pending Power connection estimation paid on 18/07/2026, Agreement was done on 30/07/2025, Connection still pending
2 Etah JMC - Lakshmi (JV) Bahadurpur kasimpur Water supply scheme Bahadurpur Kasimpur 20098697/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved Public hindrance
3 Etah JMC - Lakshmi (JV) Khera Gwarau Water supply scheme Khera Gwarau 20098703/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Pending Wok not started by UPPCL
4 Etah JMC - Lakshmi (JV) Badhavali Gram Panchayat Water Supply Scheme Badhawali 20079513/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
5 Etah JMC - Lakshmi (JV) Loya Badshapur Water supply scheme Loya Badshahpur Peetam Singh 20099319/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
6 Etah JMC - Lakshmi (JV) Kunjalpur water supply scheme Kunjalpur 20100053/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
7 Etah JMC - Lakshmi (JV) Nagaria Urf Sikandarpur Doga water supply scheme Nagaria Urf Sikandarpur Duga 20100049/01 Electricity Connection Pending 04-Aug-2026 15-Sep-2026 Resolved work not started by UPPCL
8 Etah JMC - Lakshmi (JV) Saidpur Water supply scheme Saidpur 20098701/01 Electricity Connection Pending 04-Aug-2026 20-Sep-2026 Pending work not started by UPPCL
9 Etah JMC - Lakshmi (JV) MAJHARAU GRAM PANCHAYAT WATER SUPPLY SCHEME Majharau 20079315/01 Electricity Connection Pending 04-Aug-2026 25-Sep-2026 Pending work not started by UPPCL
10 Etah Power Mech Projects Ltd SHITALPUR WATER SUPPLY SCHEME Shitalpur 20086111/01 Other 05-Aug-2026 05-Aug-2026 Resolved Dispute by villagers, Estimate revision work in progress,
11 Etah Power Mech Projects Ltd SHITALPUR WATER SUPPLY SCHEME Shitalpur 20086111/01 Electricity Connection Pending 03-Aug-2026 03-Oct-2026 Resolved Payment has to be done.