| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | GA INFRA - BABA (JV) | KHARAGPUR | Kharagpur | 20065335/01 | Saline Water / Poor Water Quality (Salinity/Fluoride/Iron) | 15-Jul-2025 | - | Pending | Land Allotted In July 2025. ERT Done Twice On two Different Lands Allotted But Failed. New Lands demarcation in process with concerned department's. |
| 2 | Fatehpur | GA INFRA - BABA (JV) | SAURA | Saura | 20087468/01 | Saline Water / Poor Water Quality (Salinity/Fluoride/Iron) | 26-Mar-2025 | 31-Oct-2026 | Pending | Land Allotted In march 2025. ERT Done Twice On two Different Lands Allotted But Failed. New Lands demarcation in process with concerned department's. |
| 3 | Fatehpur | GA INFRA - BABA (JV) | BHALEWAN | Bhalewan | 20065331/01 | Saline Water / Poor Water Quality (Salinity/Fluoride/Iron) | 24-Mar-2025 | - | Pending | Land Allotted In July 2025. ERT Done Twice On two Different Lands Allotted But Failed. New Lands demarcation in process with concerned department's. |
| 4 | Fatehpur | GA INFRA - BABA (JV) | KHARSANDWA water supply scheme RO | Kharsendwa | 20087379/01 | Land Dispute / Litigation | 26-Nov-2024 | - | Resolved | laying, boundary wall and tube well work is completed , afterwards stay orders were there on the land from the district court which was latter resolved now the second party has appealed now in high court and making nuisance while working. |
| 5 | Fatehpur | Power Mech Projects Ltd | ADAWAL RO | Adawal | 20102047/01 | Electricity Connection Pending | 15-Apr-2026 | 30-Aug-2026 | Resolved | Payment Done but Electric Connection Work Not done by Electricity Department. |
| 6 | Fatehpur | Power Mech Projects Ltd | KODAR | Kondar | 20100809/01 | Electricity Connection Pending | 15-Apr-2026 | 30-Aug-2026 | Resolved | Payment Done but Electric Connection Work Not done by Electricity Department. |
| 7 | Fatehpur | Power Mech Projects Ltd | 1.RARI BUJURG &ALIYABAD | Aliyabad | 20075563/01 | Road Widening / Pipeline Damage | 15-Nov-2025 | 30-Nov-2026 | Resolved | Damage Pipe line Due to Road Wideing . |
| 8 | Fatehpur | Power Mech Projects Ltd | PIPOURI &BHEWELI | Bhewli | 20079085/01 | Other | 19-Feb-2025 | 31-Dec-2026 | Resolved | HT Lines Passing Over the OHT Campus . |
| 9 | Fatehpur | Power Mech Projects Ltd | AMOURA | Amoura | 20079116/01 | Other | 19-Feb-2025 | 31-Dec-2026 | Resolved | HT Lines Passing Over the OHT Campus . |
| 10 | Fatehpur | Power Mech Projects Ltd | BASFRA Gram Panchayat Water Supply Scheme | Basfara | 20079087/01 | Other | 19-Feb-2025 | 31-Dec-2026 | Resolved | HT Lines Passing Over the OHT Campus . |
| 11 | Fatehpur | Power Mech Projects Ltd | BEHTAKHURD | Behta Khurd | 20089371/01 | Other | 19-Feb-2025 | 31-Dec-2026 | Resolved | HT Lines Passing Over the OHT Campus . |