| S.No. | District | Agency | Scheme | Village | OHT Code | Disruption Type | Disruption Date | Expected Resolve Date | Status | Remark |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON | LOHARAULI THAAKURAI G.P. W.S.S. | Loharauli Thakurai | 20097806/01 | Land Not Available / Short Land | 03-Aug-2026 | - | Pending | yahan kafi lambe samay se land nahin mil pa rahi, kyonki ye SVS scheme hai to ise complete karne ke liye samay bhi bahut kam hai |
| 2 | Sant Kabeer Nagar | JAKSON | DAMARUBAR GP WSS | Damarubar | 20084966/01 | Water Logged / Flood-Prone Area / Natural Calamity | 03-Jul-2025 | - | Pending | ye scheme me low land hone ke karan yahan flood area hai or pani bhara hone ke karan, our yahan tak pahunchane ke liye approch marg bhi nahin hai |
| 3 | Sant Kabeer Nagar | JAKSON | Karanjot, Santha & Sanda | Santha | 20085148/01 | Road Widening / Pipeline Damage | 04-Jun-2025 | - | Pending | is scheme me karanjot gram panchayat se sanda gram panchayat ke liye jane wali mukhy sadak me dali gai HDPE pipe lagbhag 1050 meter road wedining ke karan damage ho gai hai or santha me pani nahin ja pa rha hai |
| 4 | Sant Kabeer Nagar | JAKSON | NAGAW & BANDUMAR GOV WSS | Nagaw | 20083148/01 | Water Logged / Flood-Prone Area / Natural Calamity | 19-Feb-2025 | - | Pending | ye scheme me low land me jamin mili hai or yahan pani bhra hua hai sath hi yahan tak pahunchane ke liye approach road bhi nahin hai isliye yahan kary badhit hai |
| 5 | Sant Kabeer Nagar | JAKSON | GAURA GP WSS | Gaura | 20084459/01 | Other | 05-Dec-2024 | - | Pending | ye land tak pahunchane ke liye approach marg nahin hai , khalilabad behraich new railway track bhi ise cross kar rha hai , land par 14 bade bade tree bhi hain. ye SVS scheme hai yahan kary karne ke liye samay bhi kam hai |
| 6 | Sant Kabeer Nagar | JAKSON | Katya & Hansawa Par Gram Panchayat Water Supply Scheme | Katya | 20094544/01 | Water Logged / Flood-Prone Area / Natural Calamity | 11-Sep-2024 | - | Pending | yahan land low land me mili hai abhi rainy season me yahan pani bhara hua hia or approacha marg bhi nahin hai |
| 7 | Sant Kabeer Nagar | JAKSON | GANGAULI & MAKDOOMPUR GOV WSS | Gangoli | 20084265/01 | Road Widening / Pipeline Damage | 11-Sep-2024 | - | Pending | is scheme me se gangauli gram panchayat ke liye jane wali mukhy sadak me dali gai HDPE pipe lagbhag 1100 meter road wedining ke karan damage ho gai hai or sanda me pani nahin ja pa rha hai |
| 8 | Sant Kabeer Nagar | JAKSON | AMATHARI & PARSWANIA GOV WSS | Amathari | 20085153/01 | Road Widening / Pipeline Damage | 11-Aug-2024 | - | Pending | is jagah road widening ke karan lagbhag 1900 meter HDPE pipe damage ho gya gya hai or kary badhit hai |
| 9 | Sant Kabeer Nagar | JAKSON | PRATPPUR & MAHLA GOV WSS | Mahala | 20083192/01 | Road Widening / Pipeline Damage | 07-Aug-2024 | - | Pending | yahan lagbhag 3600 meter HDPE pipeline ko damage kar diya gya hai PWD dwara sadak ke chaurikaran ke karan |
| 10 | Sant Kabeer Nagar | JAKSON | Aurahi GP WSS | Aurahi | 20085113/01 | Road Widening / Pipeline Damage | 31-Jul-2024 | - | Resolved | is scheme me mukhy sadak ke sath rahne vale gharon ke supplybadhitb hai yahan se jane wali mukhy sadak me dali gai HDPE pipe lagbhag 450 meter road wedining ke karan damage ho gai hai or sanda me pani nahin ja pa rha hai |
| 11 | Sant Kabeer Nagar | JAKSON | Dhobaha GP WSS | Dhobaha | 20084474/01 | Road Widening / Pipeline Damage | 04-Jun-2024 | - | Pending | is gram panchayat me road weding ke karan lagbhag 1800 meter HDPE pipe damage ho gya hai or kar badhit hai |
| 12 | Sant Kabeer Nagar | JAKSON | Aurahi Gram Panchayat Water Supply Scheme | Aurahi | 20094493/01 | Land Not Available / Short Land | 03-Jun-2024 | - | Resolved | yahan allotted land NH me aane ke karan bore hone ke bad koi kary nahin ho paya hai or ab nai land allot nahin ho paa rahi hai jiske karan yahan kary badhit hai |
| 13 | Sant Kabeer Nagar | JAKSON | Karanjot, Santha & Sanda | Sanda | 20085148/01 | Road Widening / Pipeline Damage | 17-Jan-2024 | - | Pending | is scheme me karanjot gram panchayat se sanda gram panchayat ke liye jane wali mukhy sadak me dali gai HDPE pipe lagbhag 950 meter road wedining ke karan damage ho gai hai or sanda me pani nahin ja pa rha hai |
| 14 | Sant Kabeer Nagar | JAKSON | BALUSASAN GRAM PANCHAYAT WATER SUPPLY SCHEME | Balusasan | 20094156/01 | Water Logged / Flood-Prone Area / Natural Calamity | 10-Nov-2023 | - | Pending | yahan land rivaer ke pass low land me hai yahan kary karna mushkil hai or yahan approad bhi nahin hai |
| 15 | Sant Kabeer Nagar | JAKSON | Chharachh GRAM PANCHAYAT WATER SUPPLY SCHEME | Chharach | 20094109/01 | Land Not Available / Short Land | 06-Sep-2023 | - | Resolved | shuru se hi yahan koi land nahin mil pa rahi hai isliye yahan kary shuru nahin ho paya hai |
| 16 | Sant Kabeer Nagar | JAKSON | Kasauna Khurd GP WSS | KASAUNA KHURD | 20084486/01 | Public Hindrance / Local Hindrance | 03-Jun-2023 | - | Resolved | yahan kafi lambe samay se alloted land par local public ka hinrance hai, kyonki ye SVS hai to yahan kary complete karne ka samay bhi bahut kam hai |
| 17 | Sant Kabeer Nagar | VISHVARAJ | Sais Rao Mafi GP WSS | Sahs Rauwa Maphi | 20087676 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | The construction work could not be commenced due to encroachment on the village government approach road. However, the tube well has been constructed. |
| 18 | Sant Kabeer Nagar | VISHVARAJ | SIYARA SANTHA GP WSS | Siyara Santha | 20085970 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | No approach road is available to the government land for construction activities. Although the tube well has been constructed, the remaining works could not be started due to the lack of an approach road. |
| 19 | Sant Kabeer Nagar | VISHVARAJ | TEJPUR GP WSS | Tejpur | 20090056 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Oct-2026 | Pending | No approach road is available to the government land for construction activities. Although the tube well has been constructed, the remaining works could not be started due to the lack of an approach road. |
| 20 | Sant Kabeer Nagar | VISHVARAJ | BACHCHAIPUR GP WSS | Bachhaipur | 20086341 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | The tube well has been constructed; however, the remaining works could not be commenced due to the lack of a suitable approach road. |
| 21 | Sant Kabeer Nagar | VISHVARAJ | PADARAI WATER SUPPLY SCHEME | Paraisya | 20093169 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | No approach road is available to the government land for carrying out the construction work. The village is under the land consolidation (Chakbandi) process. The tube well has been constructed; however, the remaining works could not be commenced due to the absence of an approach road. |
| 22 | Sant Kabeer Nagar | VISHVARAJ | BANTWAR & BELMA GOV WATER SUPPLY SCHEME | Bantwar | 20094318 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Belma village are demanding a separate overhead water tank, due to which they are obstructing the pipeline laying and household connection works. |
| 23 | Sant Kabeer Nagar | VISHVARAJ | RAJNAULI & SANTHI GP WSS | Rajnauli | 20086765 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The residents of Rajnauli village are demanding a separate overhead water tank, resulting in resistance to the pipeline laying and household connection works. |
| 24 | Sant Kabeer Nagar | VISHVARAJ | DHAMARZA & UMARI KALA GOV WSS | Dhamaraza | 20086133 | Land Dispute / Litigation | 05-Aug-2026 | 15-Dec-2026 | Pending | The allotted land is under encroachment, and land for the solar panel is not available. |
| 25 | Sant Kabeer Nagar | VISHVARAJ | GARH SARPAR | Garh Sardar | 20084983 | Other | 05-Aug-2026 | 31-Dec-2026 | Resolved | A 132 kV transmission line passes adjacent to the project campus, and the concerned Electricity Department has instructed that no construction work be carried out in the area. The work is to be executed after preparing a suitable work plan under the guidance of the Executive Engineer. |
| 26 | Sant Kabeer Nagar | VISHVARAJ | BHELWASI & JIGINA GOV WSS | Bhelwasi | 20085352 | Other | 05-Aug-2026 | 30-Nov-2026 | Pending | The required payment for the electrical line shifting has already been deposited by the company. However, due to the non-shifting of the electrical line, the construction work of the scheme could not be commenced. |
| 27 | Sant Kabeer Nagar | VISHVARAJ | DEORIA LAL, DHORHAIE & MUSRAD GOV WSS | Deorialal | 20086316 | Land Dispute / Litigation | 05-Aug-2026 | - | Pending | The cultivator (Kashtakar) is claiming ownership of the land. The issue needs to be resolved after conducting a land demarcation (measurement). |
| 28 | Sant Kabeer Nagar | VISHVARAJ | DARUA JAPTI ADALAT & SHIVAPAR GOV WSS | Darua Japti Adalat | 20086124 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land for construction activities. The tube well has been constructed; however, the remaining works could not be carried out without obstruction due to the absence of an approach road. |
| 29 | Sant Kabeer Nagar | VISHVARAJ | Dhauripar Barhya GP WSS | Dhauripar Parhya | 20085876 | Land Not Available / Short Land | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land, due to which the construction work is being hindered. The issue needs to be resolved after conducting a land survey and demarcation. |
| 30 | Sant Kabeer Nagar | VISHVARAJ | ASHRAFABAD, MOHAMMADPUR & MOHIUDDINPUR GOV W/S Scheme | Asharfabad | 20094214 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Pending | No approach road is available to the government land at the 2nd land location for carrying out the construction work. Consequently, the construction work is being hindered. |
| 31 | Sant Kabeer Nagar | VISHVARAJ | TENUHARI DOEM | Tenuhari Doem | 20085422 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 18-Nov-2026 | Pending | No approach road is available to the government land. Due to the absence of an approach road, the remaining works could not be commenced. |
| 32 | Sant Kabeer Nagar | VISHVARAJ | GANGAICHA & JATEDEEHA GOV WSS | Jatedeeha Dubaulia | 20086874 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Oct-2026 | Pending | The villagers are opposing the use of the private approach road, which is hindering the construction work. |
| 33 | Sant Kabeer Nagar | VISHVARAJ | Sehura & Koelsa GOV WSS | Sehura | 20086908 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | No approach road is available to the government land. Consequently, the construction work cannot be executed smoothly due to the absence of an approach road. |
| 34 | Sant Kabeer Nagar | VISHVARAJ | Pipra Doman & Muradeeha Khurd GP WSS | Pipra Doman | 20086895 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 31-Dec-2026 | Pending | No approach road is available to the government land. |
| 35 | Sant Kabeer Nagar | VISHVARAJ | PURAINA ,& RUDHAULI GOV WSS | Puraina | 20085370 | Land Dispute / Litigation | 05-Aug-2026 | 30-Nov-2026 | Resolved | The villagers are disputing the provision of an approach road. Consequently, the construction work cannot be carried out without obstruction due to the unavailability of an approach road. |
| 36 | Sant Kabeer Nagar | VISHVARAJ | CHAGERA MANGERA GP WSS | Chagera Mangera | 20085382 | Public Hindrance / Local Hindrance | 05-Aug-2026 | 30-Nov-2026 | Resolved | The pipeline from Tube Well-2 to the Overhead Tank (OHT) campus could not be laid due to issues related to the availability of an approach route. |
| 37 | Sant Kabeer Nagar | VISHVARAJ | DANDWA MALI & KANPARA & PIDWA GOV WSS | Kanpara | 20085378 | Other | 05-Aug-2026 | 31-Oct-2026 | Pending | The Executive Engineer has instructed the Tehsil authorities to initiate the auction of the trees. However, no progress has been made in this regard so far. |
| 38 | Sant Kabeer Nagar | VISHVARAJ | .Agapur Urf Gulariha GRAM PANCHAYAT WATER SUPPLY SCHEME | Agapur Urf Gulariha | 20093163 | Land Not Available / Short Land | 10-Dec-2023 | 31-Dec-2026 | Pending | No land has been made available yet. Cultivation is being carried out on the village habitation (Abadi) land. |
| 39 | Sant Kabeer Nagar | VISHVARAJ | PIPRA HANKAR & SISWA DAKHILI GP WSS | Pipra Hankar | 20086174 | Land Not Available / Short Land | 05-Apr-2023 | 31-Dec-2026 | Pending | Land 1st & 2nd - No land has been made available so far. The Lekhpal has informed that the government land is under encroachment. |
| 40 | Sant Kabeer Nagar | VISHVARAJ | INAYATPUR GP WSS | Inayatpur | 20086308 | Land Not Available / Short Land | 05-Apr-2023 | 30-Dec-2026 | Pending | No land has been made available so far. The work could not be commenced due to the encroachment on the government land. |
| 41 | Sant Kabeer Nagar | VISHVARAJ | MANIKAPAR GP WSS | Manikapar | 20086757 | Land Dispute / Litigation | 14-Mar-2023 | 30-Dec-2026 | Pending | The tube well has been constructed; however, land for the Overhead Tank (OHT) is not available. |