| 1 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_71 |
Hamirpur |
Gohand |
Kemokhar |
Tyontana |
Damage Village Internal Works |
11-May-2026 |
18-May-2026 |
Main Pipe line Damge during Culvert construction |
| 2 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_71 |
Hamirpur |
Gohand |
Kemokhar |
Birbahi |
Damage Village Internal Works |
11-May-2026 |
20-May-2026 |
Mainpipe line damage during Culvert construction and Village Gate Construction |
| 3 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_94 |
Hamirpur |
Gohand |
Umariya |
Umariya |
Damage Village Internal Works |
11-May-2026 |
15-May-2026 |
Pipe line damge by electricity department during pole installation |
| 4 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_95 |
Hamirpur |
Gohand |
Chadwari Danda |
Bilgaon |
Road Widening[Other] |
11-May-2026 |
27-May-2026 |
pipe line damage during culver construction and road widening by sand khadan contractor |
| 5 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_72 |
Hamirpur |
Gohand |
Jakheri |
Aura Khera |
Damage Village Internal Works |
11-May-2026 |
14-May-2026 |
Main pipe line damage during village internal work |
| 6 |
8135500 |
Haraulipur GOV and Tubewell Scheme 125 Nos. |
OHT_115 |
Hamirpur |
Gohand |
Dhanouri |
Dhanouri |
Damage Village Internal Works |
11-May-2026 |
21-May-2026 |
Pipe pine damage by gram pradhan during drain work |