Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

Regular Water Supply Supply Disruptions

Sr No. Scheme Code Scheme Name District Block Panchayat Village Code Village Issue Type Issue Date Expected Issue Resolve Date Remark
1 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Khiriyalatkanju 424954 Khiriyalatkanju Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
2 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Kumehri 424956 Kumehri Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed. The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department.
3 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Kumehri 424956 Kumehri Road Widening[PWD] 01-May-2025 12-Apr-2026 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed. The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department.
4 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Pachaunda 424965 Pachaunda Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
5 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Midarwaha 424966 Midarwaha Road Widening[PWD] 01-May-2025 07-Sep-2025 The ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
6 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Midarwaha 424967 Ajana Road Widening[PWD] 01-May-2025 07-Sep-2025 ESR 250mm CWRM pipe was damaged by the PWD / Pharmaceutical Agency , due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
7 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Chhayan 424959 Chhayan Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed.
8 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Nainwara 424978 Darona Road Widening[PWD] 01-May-2025 Distribution HDPE 160mm Pipe line damaged at Road Both Side by PWD/Pharmaceutical Agency due to the water supply is suspended in this village.
9 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Nainwara 424979 Nainwara Road Widening[PWD] 01-May-2025 Distribution HDPE 160mm Pipe line damaged at Road Both Side by PWD/Pharmaceutical Agency due to the water supply is suspended in this village.
10 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425030 Baron Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be relaid in till fisrt week of September , and the supply from the ESR will be resumed.
11 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425030 Baron Road Widening[PWD] 01-May-2025 18-Mar-2026 the ESR pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be relaid in till fisrt week of September , and the supply from the ESR will be resumed.
12 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425030 Baron Road Widening[PWD] 01-May-2025 12-Apr-2026 the ESR pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be relaid in till fisrt week of September , and the supply from the ESR will be resumed.
13 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425032 Bhoosra Road Widening[PWD] 01-May-2025 07-Sep-2025 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed. The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department.
14 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425032 Bhoosra Road Widening[PWD] 01-May-2025 12-Apr-2026 the ESR 250mm CWRM pipe was damaged by the PWD, due to which the supply to the entire zone is suspended. The pipe will be re-laid in till first week of September , and the supply from the ESR will be resumed. The 300mm distribution pipe, which supplies Kumehri, Boosra, and Baron villages, has also been damaged by the PWD department.
15 8010056 Saidpur Kumheri GOV Lalitpur Madawra Bhonti Madawra 425130 Bhonti Madawra Damage Village Internal Works 03-Sep-2026 10-Sep-2026 Di Pipeline has been Damage Due to flood condition in the area caused by heavy rainfall.
16 8010056 Saidpur Kumheri GOV Lalitpur Madawra Jalandhar 425120 Jalandhar Power/Electrical Issue 04-Jul-2026 No power supply since last 04/07/2026
17 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Sadumal 424984 Sadumal Power/Electrical Issue 04-Jul-2026 No power supply since last 04/07/2026
18 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Nainwara 424978 Darona Power/Electrical Issue 04-Jul-2026 No power supply since last 04/07/2026
19 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Midarwaha 424967 Ajana Power/Electrical Issue 04-Jul-2026 No power supply since last 04/07/2026
20 8010056 Saidpur Kumheri GOV Lalitpur Madawra Pahadi Kalan 425109 Kawrata Road Widening[Other] 05-Feb-2025 01-Aug-2025 110mm HDPE distribution pipe was damaged at multiple places by Gram Pardhan while widening the road of village and expects to resolve the issue by the last of August
21 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Gadolikalan 424980 Gadolikalan Power/Electrical Issue 05-Jul-2026 No power supply since last 04/07/2026
22 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Saidpur 424973 Saidpur Damage Village Internal Works 07-Aug-2026 14-Aug-2026 Sluice Valve Damage by Local villager Public at Saidpur
23 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Simiriya 424986 Simariya Damage Village Internal Works 07-Aug-2026 11-Aug-2026 Air Valve Damage by villager Public at Rakhwara to Simariya Main distribution line.
24 8010056 Saidpur Kumheri GOV Lalitpur Madawra Bhonti Madawra 425130 Bhonti Madawra Power/Electrical Issue 07-Jul-2026 No power supply since last 04/07/2026
25 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Karoda 424977 Karonda Power/Electrical Issue 07-Jul-2026 No power supply since last 04/07/2026
26 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Simiriya 424986 Simariya Damage Village Internal Works 08-May-2026 31-May-2026 Work stopped by Pradhan Sahab (Awadhesh Pratap)
27 8010056 Saidpur Kumheri GOV Lalitpur Madawra Pahadi Kalan 425109 Kawrata Damage Village Internal Works 09-Jun-2026 17-Jun-2026 Pipeline damage HDPE 110 mm by farmer during field excavation
28 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Karoda 424977 Karonda Damage Village Internal Works 09-Jun-2026 17-Jun-2026 Pipeline damaged 160 mm HDPE & DI by local vendor during to soil excavation
29 8010056 Saidpur Kumheri GOV Lalitpur Madawra Jalandhar 425121 Agra Damage Village Internal Works 10-Sep-2026 17-Sep-2026 Main cwrm Pipeline has been Damaged during Excavation work by Pradhanji. As a result 7 village in the agra zone & 7 village in madanpur have been affected.
30 8010056 Saidpur Kumheri GOV Lalitpur Madawra Bamhori Kalan 425129 Bamhori Kalan Damage Village Internal Works 10-Sep-2026 17-Sep-2026 During the Excavation and pipe laying work, the Main distribution pipeline was damaged due to vendor
31 8010056 Saidpur Kumheri GOV Lalitpur Madawra Madanpur 425132 Madanpur Damage Village Internal Works 10-Sep-2026 17-Sep-2026 Main cwrm Pipeline has been Damaged during Excavation work by Pradhanji. As a result 7 village in madanpur have been affected.
32 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Saidpur 424973 Saidpur Damage Village Internal Works 20-Aug-2026 27-Aug-2026 Pipeline (Dia- 63 mm HDPE) Damaged during Nala Excavation by Villager Public
33 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Kumehri 424956 Kumehri Damage Village Internal Works 20-May-2026 25-May-2026 Pipeline damaged by PWD road department
34 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Chhayan 424959 Chhayan Damage Village Internal Works 20-May-2026 24-May-2026 Pipeline damaged by BSNL 63 MM HDPE PIPE
35 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Kumehri 424956 Kumehri Damage Village Internal Works 22-May-2026 25-May-2026 pipeline damaged by jal sansthan
36 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425032 Bhoosra Damage Village Internal Works 22-May-2026 25-May-2026 pipeline damaged by jal sansthan
37 8010056 Saidpur Kumheri GOV Lalitpur Mahroni Baron 425030 Baron Damage Village Internal Works 22-May-2026 25-May-2026 pipeline damaged by jal sansthan