1 |
Unnao |
Unnao |
I&D of Drains and STP works in Unnao (15MLD) |
City Jail Drain (Dakari drain) |
Tapped Drains |
1200 mm RCC Pipe 315.30meter pipe laying out of 400 meter sewer line is done balance 84.17 meter work in progress, KRMPL deployed 12 manpower at site out of which. Dewatering & Cleaning of 543meter work in progress (350meter done) balance 193 meter work in progress KRMPL deployed cleaning of Sewer line 15manpower. STP 24 Hrs operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. |
13-May-2025 10:34 AM |