| S.No | District | City | Project Name | Drain Name | DrainType | Remarks | Last Update Date |
|---|---|---|---|---|---|---|---|
| 1 | Unnao | Unnao | I&D of Drains and STP works in Unnao (15MLD) | City Jail Drain (Dakari drain) | Tapped Drains | Construction of 01 Manhole (MH 44) is pending, dewatering in Manhole No. 44 is in progress. KRMPL deployed 6 manpower at site. Dewatering & Cleaning of balance 20meter sewer line work is under progress, KRMPL has deployed 4 manpower for cleaning of Sewer line. STP operating daily from 11.1.2025 through temporary line, CCT operating manually automation work of CCT is pending. Balance work likely to be completed by April-26 | 25-Mar-2026 11:16 AM |