| 1 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Ganga Vishnu Drain |
Untapped Drains |
The work of cleaning 1.96 km drain and construction of Connecting Drain of 90.00 meters at 03 identified sites to bring 01 drain Ganga Vishnu Drain to I&D is to be done by Executive Officer Nagar Palika Parishad Gangaghat (Shuklaganj) |
25-Mar-2026 11:17 AM |
| 2 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Indira Nagar Drain |
Tapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
24-Mar-2026 10:50 AM |
| 3 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Manohar Nagar Nala Ist (New) |
Tapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
24-Mar-2026 10:50 AM |
| 4 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Railway Bridge Drain |
Tapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
24-Mar-2026 10:50 AM |
| 5 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
Manohar Nagar Nala IInd (New) |
Tapped Drains |
The tapping of domestic sewage through I&D was completed on 30.12.2025, and the project trial run has commenced. The trial run will continue for three months, after which the STP will operate at full capacity |
24-Mar-2026 10:50 AM |