| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20011085 | Name of Scheme: kundesra village water supply scheme | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 7302 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 29-Sep-2023 | Actual Date of Completion (Capex): 10-Dec-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 54.26 MTR / 96.38 MTR | KUNDESRA (M.S.T) SAKLI | 29.142827 | 78.736705 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBEMERSIBLE PUMP | 950 LPM / 40 MTR | KUNDESRA (M.S.T) SAKLI | 29.142827 | 78.736705 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 300 KL / 16 MTR | KUNDESRA (M.S.T) SAKLI | 29.143034 | 78.736944 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 DI PIPE | 150 | 0.025 | OK |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN-6: CLASS PE-100 | 90 | 0.422 | OK |
| 2 | HDPE PIPE PN-6: CLASS PE-100 | 75 | 1.200 | OK |
| 3 | HDPE PIPE PN-6: CLASS PE-100 | 63 | 8.000 | OK |
| 4 | HDPE PIPE PN-6: CLASS PE-100 | 110 | 0.622 | OK |
| 5 | HDPE PIPE PN-6: CLASS PE-100 | 125 | 0.200 | OK |
| 6 | HDPE PIPE PN-6: CLASS PE-100 | 160 | 0.400 | OK |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 650 |