Project Completion Certificate (Ground Water)
Scheme ID: 20012444 Name of Scheme: BARAHUA BHOJPUR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2450 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Jul-2025 Actual Date of Completion (Capex): 06-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24/171.86 Barahua Bhojpur 25.854706 81.901729
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible pump 30/57 Barahua Bhojpur 25.854706 81.901729
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/16 Barahua Bhojpur 25.854706 81.901729
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 80 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.9219
2 HDPE 75 0.4688
3 HDPE 90 0.9031
4 HDPE 110 0.524
5 HDPE 140 1.832
6 HDPE 160 0.318
HSC Connection
Sno. Total Nos.
1 378
Other Details
2.16
0.00
0.00
08-Jun-2024
07-Jul-2024