Project Completion Certificate (Ground Water)
Scheme ID: 20014464 Name of Scheme: Mali Pur No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2538 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 02-Nov-2023 Actual Date of Completion (Capex): 18-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 12.02 MTR / 99.54 MTR MALI PUR 28.797638 78.704523
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBEMERSIBLE PUMP 500 LPM / 46 MTR MALI PUR 28.797638 78.704523
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150 KL / 14 MTR MALI PUR 28.797757 78.704592
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 80 0.0097 OK
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6: CLASS PE-100 75 0.459 OK
2 HDPE PIPE PN-6: CLASS PE-100 63 3.359 OK
3 HDPE PIPE PN-6: CLASS PE-100 110 0.143 OK
4 HDPE PIPE PN-6: CLASS PE-100 160 0.118 OK
5 HDPE PIPE PN-6: CLASS PE-100 140 0.089 OK
HSC Connection
Sno. Total Nos.
1 390
Other Details
1.75
0.00
1.75
16-Jun-2024
17-Jun-2024