Project Completion Certificate (Ground Water)
Scheme ID: 20020532 Name of Scheme: BHALUWA No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2120 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Feb-2024 Actual Date of Completion (Capex): 30-Apr-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 17/94.68 Bhaluwa 26.6545 83.1711
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 30/44 Bhaluwa 26.6545 83.1711
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 150/16 Bhaluwa 26.6545 83.1711
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.016 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.936 Laying Completed
2 HDPE 75 0.58 Laying Completed
3 HDPE 90 1.276 Laying Completed
4 HDPE 110 0.17 Laying Completed
HSC Connection
Sno. Total Nos.
1 310
Other Details
1.84
0.00
1.83
31-Mar-2024
01-May-2026