Project Completion Certificate (Ground Water)
Scheme ID: 20022197 Name of Scheme: Newada No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 2660 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 13-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well -300X150 36/175.71 Newada 25.574089 82.723432
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Pump-12.5HP 550/47.10 Newada 25.574089 82.723432
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150/12 Newada 25.573986 82.72347
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 150 0.015
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 140 0.046
2 HDPE PIPE PN-6 110 0.100
3 HDPE PIPE PN-6 75 1.008
4 HDPE PIPE PN-6 90 1
5 HDPE PIPE PN-6 63 3.801
HSC Connection
Sno. Total Nos.
1 250
Other Details
2.06
1.89
1.72
13-Oct-2025
14-Oct-2025