| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20025889 | Name of Scheme: ASHALATNAGAR PWS SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 9865 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 06-Aug-2022 | Actual Date of Completion (Capex): 30-Sep-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | tubewell | 31/105.52 | Ashalatnagar | 28.763019 | 77.639312 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | submersible | 1300/53 | Ashalatnagar | 28.763019 | 77.639312 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 375/12 | Ashalatnagar | 28.763019 | 77.639312 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 250 | 0.398 | |
| 2 | D.I | 100 | 0.028 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 8.448 | |
| 2 | HDPE | 75 | 0.430 | |
| 3 | HDPE | 90 | 0.916 | |
| 4 | HDPE | 110 | 0.197 | |
| 5 | HDPE | 125 | 0.251 | |
| 6 | HDPE | 160 | 0.058 | |
| 7 | HDPE | 200 | 0.449 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 844 |