Project Completion Certificate (Ground Water)
Scheme ID: 20026063 Name of Scheme: BHISVA CHITAUNA SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 7
Total Population Covered: 6340 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 28-Sep-2023 Actual Date of Completion (Capex): 25-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 26.10/75.12 BHISVA CHITAUNA 26º 18' 39.04" N 82º 38' 59.997" E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 51/46 BHISVA CHITAUNA 26º 18' 39.04" N 82º 38' 59.997" E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC-Zink Alum Tank 250/16 BHISVA CHITAUNA 26º 18' 39.04" N 82º 38' 59.997" E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 12.071
2 HDPE Pipe PN-6: Class PE-100 75 5.775
3 HDPE Pipe PN-6: Class PE-100 90 1.120
4 HDPE Pipe PN-6: Class PE-100 110 1.798
5 HDPE Pipe PN-6: Class PE-100 140 1.45
6 HDPE Pipe PN-6: Class PE-100 160 0.349
7 HDPE Pipe PN-6: Class PE-100 200 0.059
HSC Connection
Sno. Total Nos.
1 600
Other Details
3.34
0.00
3.29
12-Oct-2025
13-Oct-2025