| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20026111 | Name of Scheme: Chauki kalan Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 5 |
| Total Population Covered: 3200 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 03-Sep-2023 | Actual Date of Completion (Capex): 10-Oct-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 200X150 | 24.13m/183.67m | Chauki kalan | 25.566659 | 82.331552 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | 12.5 HP | 670LPM/43M | Chauki kalan | 25.566659 | 82.331552 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200 kl/ 12 m | Chauki kalan | 25.566847 | 82.33145 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 150 | 0.02013 | Yes |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.6392 | Yes |
| 2 | HDPE | 75 | 4.3346 | Yes |
| 3 | HDPE | 63 | 15.216 | Yes |
| 4 | HDPE | 110 | 0.355 | Yes |
| 5 | HDPE | 125 | 0.665 | Yes |
| 6 | HDPE | 140 | 0.120 | Yes |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 550 |