Project Completion Certificate (Ground Water)
Scheme ID: 20026728 Name of Scheme: GOPIPUR No. of Villages: 3 No. of Habitation Covered: 14
Total Population Covered: 5288 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 29-Sep-2023 Actual Date of Completion (Capex): 16-Jan-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 200X150 15.05 m /225.07 m Gipipur 25.659076 82.703665
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 15 HP 800 LPM/47 M Gipipur 25.659076 82.703665
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225 KL/16 M Gipipur 25.659076 82.703665
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI, K-7 150 0.084 yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 2.341 yes
2 HDPE 75 3.221 yes
3 HDPE 63 7.508 yes
4 HDPE 110 .729 yes
5 HDPE 140 .511 yes
6 HDPE 160 .588 yes
7 HDPE 180 .450 yes
HSC Connection
Sno. Total Nos.
1 542
Other Details
2.58
2.58
2.59
16-Jan-2026
17-Jan-2026