| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20036550 | Name of Scheme: AKABARPUR & KHURWAHA GRAMIN PEYJAL YOJNA | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 6296 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 13-May-2024 | Actual Date of Completion (Capex): 22-Apr-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewells | 43.05/278.61 | AKABARPUR & KHURWAHA | 27.14554 | 79.546068 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSSIBLE Pumps | 625/63 | AKABARPUR & KHURWAHA | 27.14554 | 79.546068 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT's | 375/16 | AKABARPUR & KHURWAHA | 27.14554 | 79.546068 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.315 | Clear Water Rising Main |
| 2 | DI | 150 | 0.0063 | Clear Water Rising Main |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 3.125 | Distribution Network |
| 2 | HDPE | 63 | 7.752 | Distribution Network |
| 3 | HDPE | 110 | 1.719 | Distribution Network |
| 4 | HDPE | 140 | 1.407 | Distribution Network |
| 5 | HDPE | 160 | 0.342 | Distribution Network |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1198 |