Project Completion Certificate (Ground Water)
Scheme ID: 20051107 Name of Scheme: BAJETI WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2050 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 23-Nov-2023 Actual Date of Completion (Capex): 13-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.00/99.80 BAJETI 26.068382 82.060472
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPUMP-1 430LPM/43M BAJETI 26.068382 82.060472
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DIPIPE K-7 100 0.029
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6: Class PE-100 63 13.801
2 HDPE PIPE PN-6: Class PE-100 75 1.207
3 HDPE PIPE PN-6: Class PE-100 90 0.439
4 HDPE PIPE PN-6: Class PE-100 110 0.406
5 HDPE PIPE PN-6: Class PE-100 140 1.283
HSC Connection
Sno. Total Nos.
1 370
Other Details
1.88
0.00
2.06
05-Sep-2025
01-Mar-2026