Project Completion Certificate (Ground Water)
Scheme ID: 20056708 Name of Scheme: BELA PARSA WSS No. of Villages: 1 No. of Habitation Covered: 7
Total Population Covered: 6940 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Dec-2023 Actual Date of Completion (Capex): 28-Sep-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 32/60.80 BELA PARSA 26°27'53.68"N 82°43'10.74"E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPump 72/42 BELA PARSA 26°27'53.68"N 82°43'10.74"E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC-Zink Alum 350/12 BELA PARSA 26°27'53.68"N 82°43'10.74"E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.040
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 12.125
2 HDPE Pipe PN-6: Class PE-100 75 2.732
3 HDPE Pipe PN-6: Class PE-100 90 3.179
4 HDPE Pipe PN-6: Class PE-100 110 1.495
5 HDPE Pipe PN-6: Class PE-100 125 1.46
6 HDPE Pipe PN-6: Class PE-100 140 0.66
7 HDPE Pipe PN-6: Class PE-100 160 0.069
8 HDPE Pipe PN-6: Class PE-100 180 0.195
9 HDPE Pipe PN-6: Class PE-100 200 0.253
HSC Connection
Sno. Total Nos.
1 400
Other Details
3.43
0.00
3.42
29-Dec-2025
01-Jan-2026