Project Completion Certificate (Ground Water)
Scheme ID: 20056910 Name of Scheme: KALA AAM (GOGP) JJM No. of Villages: 3 No. of Habitation Covered: 6
Total Population Covered: 5970 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 10-Sep-2024 Actual Date of Completion (Capex): 10-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 30M/112M KALA AAM 27.376811 80.338512
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 75M³ per Hr / 45M KALA AAM 27.376811 80.338512
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 375KL/16M KALA AAM 27.376811 80.338512
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.048
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 4.439
2 HDPE PIPE PN:-6 75 4.348
3 HDPE PIPE PN:-6 90 3.236
4 HDPE PIPE PN:-6 110 1.488
5 HDPE PIPE PN:-6 125 1.736
6 HDPE PIPE PN:-6 140 0.00
7 HDPE PIPE PN:-6 160 0.381
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 2.219
HSC Connection
Sno. Total Nos.
1 1320
Other Details
4.04
0.00
3.94
09-Aug-2025
26-Sep-2025