Project Completion Certificate (Ground Water)
Scheme ID: 20057008 Name of Scheme: RATNUPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 4 No. of Habitation Covered: 12
Total Population Covered: 4000 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 23-Jan-2023 Actual Date of Completion (Capex): 27-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 200X150 21.16 m/246.74m Ratnupur 25.57116 82.945211
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 10 HP 550LPM/44m Ratnupur 25.57116 82.945211
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175Kl/12m Ratnupur 25.571083 82.945312
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K-7 100 0.0248 Yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 .650 yes
2 HDPE 75 2.998 yes
3 HDPE 63 7.11 yes
4 HDPE 110 0.69 yes
5 HDPE 125 1.664 yes
6 HDPE 140 0.722 yes
7 HDPE 160 0.195 yes
8 HDPE 180 0.078 yes
HSC Connection
Sno. Total Nos.
1 427
Other Details
212.10
195.99
195.99
27-May-2025
28-May-2025