| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20058015 | Name of Scheme: Bansahia water supply scheme | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 2690 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 26-Sep-2024 | Actual Date of Completion (Capex): 26-Jan-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24/151.88 | BANSAHIA | 26.620366 | 83.686158 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | PUMP | 600/40 | BANSAHIA | 26.620366 | 83.686158 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 175/12 | BANSAHIA | 26.620366 | 83.686158 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 100 | 0.022 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 63 | 4.864 | |
| 2 | HDPE PIPE | 75 | 0.573 | |
| 3 | HDPE PIPE | 90 | 0.433 | |
| 4 | HDPE PIPE | 110 | 0.645 | |
| 5 | HDPE PIPE | 140 | 0.446 | |
| 6 | HDPE PIPE | 160 | 0.106 | |
| 7 | HDPE PIPE | 180 | 0.063 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 375 |