Project Completion Certificate (Ground Water)
Scheme ID: 20058804 Name of Scheme: DHAKIA HAMID NAGAR WSS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2522 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 30-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 18.00/86.43 DHAKIA HAMID NAGAR 27.982575 79.984972
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VP PUMP -1 30.6 M3 / 45 M DHAKIA HAMID NAGAR 27.982575 79.984972
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT -1 150 KL-14 M DHAKIA HAMID NAGAR 27.982626 79.985042
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 100 0.040
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6Kg 63 4.090
2 HDPE / 6Kg 75 1.830
3 HDPE / 6Kg 90 0.931
4 HDPE / 6Kg 110 0.260
5 HDPE / 6Kg 140 0.048
6 HDPE / 6Kg 160 0.226
HSC Connection
Sno. Total Nos.
1 476
Other Details
1.71
0.00
1.71
30-Dec-2023
06-Dec-2024