| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20071514 | Name of Scheme: BARIYAONA& GARTHULI GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 4 | No. of Habitation Covered: 13 |
| Total Population Covered: 7405 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Jul-2024 | Actual Date of Completion (Capex): 02-Mar-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 26.96 M / 67.81 M | BARIYAONA& GARTHULI | 26.393555 | 82.073519 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 1020 LPM / 50 M | BARIYAONA& GARTHULI | 26.393555 | 82.073519 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 300 KL / 18 M | BARIYAONA& GARTHULI | 26.393555 | 82.073519 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI / K7 | 150 | 0.013 | |
| 2 | DI / K7 | 250 | 0.358 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / PN-6: Class PE-100 | 63 | 23.057 | |
| 2 | HDPE / PN-6: Class PE-100 | 75 | 3.137 | |
| 3 | HDPE / PN-6: Class PE-100 | 90 | 2.729 | |
| 4 | HDPE / PN-6: Class PE-100 | 110 | 2.252 | |
| 5 | HDPE / PN-6: Class PE-100 | 125 | 0.644 | |
| 6 | HDPE / PN-6: Class PE-100 | 140 | 0.731 | |
| 7 | HDPE / PN-6: Class PE-100 | 160 | 0.396 | |
| 8 | HDPE / PN-6: Class PE-100 | 180 | 0.292 | |
| 9 | HDPE / PN-6: Class PE-100 | 200 | 0.604 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 851 |