| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20072053 | Name of Scheme: RAMGARH WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 3610 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 05-Feb-2026 | Actual Date of Completion (Capex): 03-Mar-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 19/42.5 | RAMGARH | 26.124573 | 82.279675 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT Pump-1 | 760LPM/48M | RAMGARH | 26.124573 | 82.279675 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 225KL/18M | RAMGARH | 26.124573 | 82.279675 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI Pipe K-7 | 150 | 0.0299 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE-PN-6 , PE-100 | 63 | 1.272 | |
| 2 | HDPE-PN-6 , PE-100 | 75 | 2.874 | |
| 3 | HDPE-PN-6 , PE-100 | 90 | 18.253 | |
| 4 | HDPE-PN-6 , PE-100 | 110 | 0.691 | |
| 5 | HDPE-PN-6 , PE-100 | 140 | 0.512 | |
| 6 | HDPE-PN-6 , PE-100 | 160 | 0.017 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 402 |