Project Completion Certificate (Ground Water)
Scheme ID: 20076008 Name of Scheme: Etawa Village Water Supply No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3664 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 03-Feb-2023 Actual Date of Completion (Capex): 30-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 100 0.01
2 K-7 DI PIPE 150 0.01
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6: Class PE -100 63 6.34
2 HDPE PIPE PN-6: Class PE -100 75 0.13
3 HDPE PIPE PN-6: Class PE -100 90 0.44
4 HDPE PIPE PN-6: Class PE -100 110 0.19
5 HDPE PIPE PN-6: Class PE -100 125 0.55
6 HDPE PIPE PN-6: Class PE -100 160 0.56
7 HDPE PIPE PN-6: Class PE -100 180 0.02
HSC Connection
Sno. Total Nos.
1 630
Other Details
2.32
2.32
2.27
31-Jan-2025
01-Feb-2025