Project Completion Certificate (Ground Water)
Scheme ID: 20076096 Name of Scheme: BHATPURA WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2340 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 03-Feb-2023 Actual Date of Completion (Capex): 30-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN -6: CLASS PE -100 63 7.55
2 HDPE PIPE PN -6: CLASS PE -100 75 0.46
3 HDPE PIPE PN -6: CLASS PE -100 90 0.36
4 HDPE PIPE PN -6: CLASS PE -100 110 0.12
5 HDPE PIPE PN -6: CLASS PE -100 140 0.12
HSC Connection
Sno. Total Nos.
Other Details
1.98
1.98
1.87
31-Jan-2025
01-Apr-2024