| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20076609 | Name of Scheme: NAGWA GP WSS | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1867 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 02-Sep-2024 | Actual Date of Completion (Capex): 18-Jul-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 150 | NAGAWA | 27.233653 | 82.967785 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 350 LPM / 43 MTR | NAGAWA | 27.233653 | 82.967785 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 100KL 12 MTR | NAGAWA | 27.233653 | 82.967785 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 / DI PIPE | 100 | 0.3560 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PE-100 PN-6 / HDPE PIPE | 140 | 0.093 | |
| 2 | PE-100 PN-6 / HDPE PIPE | 110 | 0.425 | |
| 3 | PE-100 PN-6 / HDPE PIPE | 75 | 0.439 | |
| 4 | PE-100 PN-6 / HDPE PIPE | 63 | 3.819 | |
| 5 | PE-100 PN-6 / HDPE PIPE | 90 | 0.334 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 258 |