| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20077092 | Name of Scheme: BHAU KHURD GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 2 | No. of Habitation Covered: 5 |
| Total Population Covered: 1698 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 08-Sep-2024 | Actual Date of Completion (Capex): 16-Apr-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18.45/95.80 | BHAU KHURD | 27.08802 | 79.86873 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSSIBLE PUMP | 400/72 | BHAU KHURD | 27.08802 | 79.86873 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100/20 | BHAU KHURD | 27.08802 | 79.86873 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 80 | 0.002 | Clear Water Rising Main |
| 2 | DI | 100 | 0.01720 | Clear Water Rising Main |
| 3 | DI | 150 | 0.00530 | Clear Water Rising Main |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.71 | Distribution Network |
| 2 | HDPE | 63 | 2.123 | Distribution Network |
| 3 | HDPE | 110 | 0.211 | Distribution Network |
| 4 | HDPE | 140 | 0.898 | Distribution Network |
| 5 | HDPE | 160 | 0.294 | Distribution Network |
| 6 | HDPE | 180 | 0.981 | Distribution Network |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 256 |