Project Completion Certificate (Ground Water)
Scheme ID: 20077614 Name of Scheme: FATEHPUR TODARPUR MALIKPUR No. of Villages: 6 No. of Habitation Covered: 9
Total Population Covered: 4703 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 14-Mar-2024 Actual Date of Completion (Capex): 26-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 30/259.38 FATEHPUR TODERPUR MALIKPUR 26.516375 80.160927
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 1100/66 FATEHPUR TODERPUR MALIKPUR 26.516375 80.160927
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 325/18 FATEHPUR TODERPUR MALIKPUR 26.516375 80.160927
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K7 150 0.0101
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.331
2 HDPE 90 4.314
3 HDPE 110 1.954
4 HDPE 125 0.539
5 HDPE 160 3.395
6 HDPE 180 1.266
7 HDPE 200 0.632
HSC Connection
Sno. Total Nos.
1 1018
Other Details
5.85
0.00
4.78
10-May-2024
11-May-2024