| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20079094 | Name of Scheme: PARADAN Gram Panchayat Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2094 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 13-Mar-2024 | Actual Date of Completion (Capex): 12-Dec-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell 750 LPM | 24.98/135.33M | PARADAN | 26.047274 | 80.541706 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump 20HP | 750 LPM/57M | PARADAN | 26.047274 | 80.541706 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 225 kL /12 M | PARADAN | 26.047274 | 80.541706 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI-K-7 | 150 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 200 | 0.928 | |
| 2 | HDPE | 180 | 0.694 | |
| 3 | HDPE | 90 | 0.09 | |
| 4 | HDPE | 75 | 0.582 | |
| 5 | HDPE | 63 | 6.692 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 595 |