Project Completion Certificate (Ground Water)
Scheme ID: 20084425 Name of Scheme: MIRAPUR & PARSIPUR WSS No. of Villages: 2 No. of Habitation Covered: 12
Total Population Covered: 4578 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Mar-2024 Actual Date of Completion (Capex): 02-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24.00/86.80 PARSIPUR 26.311109 81.99744
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPUMP-1 965LPM/45M PARSIPUR 26.311109 81.99744
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250KL/14M PARSIPUR 26.311109 81.99744
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE K-7 150 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6; CLASS PE-100 63 11.442
2 HDPE PIPE PN-6; CLASS PE-100 75 5.347
3 HDPE PIPE PN-6; CLASS PE-100 90 3.330
4 HDPE PIPE PN-6; CLASS PE-100 110 1.573
5 HDPE PIPE PN-6; CLASS PE-100 140 1.678
6 HDPE PIPE PN-6; CLASS PE-100 160 1.282
7 HDPE PIPE PN-6; CLASS PE-100 200 0.198
HSC Connection
Sno. Total Nos.
1 720
Other Details
3.26
0.00
3.22
06-Jan-2026
01-Feb-2026