| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20084425 | Name of Scheme: MIRAPUR & PARSIPUR WSS | No. of Villages: 2 | No. of Habitation Covered: 12 |
| Total Population Covered: 4578 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 08-Mar-2024 | Actual Date of Completion (Capex): 02-Oct-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24.00/86.80 | PARSIPUR | 26.311109 | 81.99744 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VTPUMP-1 | 965LPM/45M | PARSIPUR | 26.311109 | 81.99744 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 250KL/14M | PARSIPUR | 26.311109 | 81.99744 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE K-7 | 150 | 0.025 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN-6; CLASS PE-100 | 63 | 11.442 | |
| 2 | HDPE PIPE PN-6; CLASS PE-100 | 75 | 5.347 | |
| 3 | HDPE PIPE PN-6; CLASS PE-100 | 90 | 3.330 | |
| 4 | HDPE PIPE PN-6; CLASS PE-100 | 110 | 1.573 | |
| 5 | HDPE PIPE PN-6; CLASS PE-100 | 140 | 1.678 | |
| 6 | HDPE PIPE PN-6; CLASS PE-100 | 160 | 1.282 | |
| 7 | HDPE PIPE PN-6; CLASS PE-100 | 200 | 0.198 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 720 |