| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20085691 | Name of Scheme: BELKHAUR WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 5 |
| Total Population Covered: 2430 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 09-Jun-2024 | Actual Date of Completion (Capex): 24-Oct-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24.11/118.77 | BELKHAUR | 26.179838 | 81.728043 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE - 1 | 510 LPM/ 52 M | BELKHAUR | 26.179838 | 81.728043 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT - 1 | 150 KL / 14 M | BELKHAUR | 26.179838 | 81.728043 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 100 | 0.024 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.284 | |
| 2 | HDPE | 90 | 0.854 | |
| 3 | HDPE | 110 | 0.773 | |
| 4 | HDPE | 140 | 0.073 | |
| 5 | HDPE | 160 | 0.115 | |
| 6 | HDPE | 180 | 0.036 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 310 |