Project Completion Certificate (Ground Water)
Scheme ID: 20089146 Name of Scheme: Aslatpur Water Supply Scheme No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 4074 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 20-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube-well 30.6/125.19 Aslatpur Urf Tohfapur 29.372318 78.421173
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 900/48 Aslatpur Urf Tohfapur 29.372318 78.421173
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250/12 Aslatpur Urf Tohfapur 29.372318 78.421173
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.4022
2 HDPE 75 0.9039
3 HDPE 90 3.6954
4 HDPE 110 0.1571
HSC Connection
Sno. Total Nos.
1 341
Other Details
2.17
0.00
2.45
20-Apr-2025
21-Apr-2025