Project Completion Certificate (Ground Water)
Scheme ID: 20089664 Name of Scheme: Barmupur PWS No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 1616 Base Year: 2023 Intermediate Year: 0 Design Year: 0
Date of Completion (As per Contract): 01-Jun-2022 Actual Date of Completion (Capex): 13-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube Well 12.05 M / 60.53 M BARMUPUR 26.724637 79.619747
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 300 LPM / 59 M BARMUPUR 26.724637 79.619747
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 50 KL / 12 M BARMUPUR 26.724637 79.619747
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.010
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.776
2 HDPE 90 1.598
3 HDPE 110 0.424
HSC Connection
Sno. Total Nos.
1 390
Other Details
1.34
0.00
1.37
12-Jan-2025
14-Jan-2025