Project Completion Certificate (Ground Water)
Scheme ID: 20090339 Name of Scheme: NAIMGANJ MV GP WS SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 3004 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 10-Mar-2024 Actual Date of Completion (Capex): 01-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube Well 15.00/93.79 Naimganj 28.691596 79.023613
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 AC Pump 24.60/42.00 Naimganj 28.691596 79.023613
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zn-Alm 125/12 Naimganj 28.691720 79.023638
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE K-7 100 0.0129
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 0.335
2 HDPE 75 0.0232
3 HDPE 63 2.041
4 HDPE 110 0.270
5 HDPE 140 0.0691
HSC Connection
Sno. Total Nos.
1 272
Other Details
136.17
136.15
136.15
01-Apr-2025
11-Jul-2025