Project Completion Certificate (Ground Water)
Scheme ID: 20093024 Name of Scheme: RAJEPUR SARAIMEDA SVS No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 6636 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 30-May-2025 Actual Date of Completion (Capex): 01-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 33M/244M RAJEPUR SARAIMEDA 27.25493 79.61936
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 700LPM/65M- 02 NOS RAJEPUR SARAIMEDA 27.25493 79.61936
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 400KL/18M RAJEPUR SARAIMEDA 27.25493 79.61936
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.289
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 2.948
2 HDPE PIPE 63 7.339
3 HDPE PIPE 110 0.520
4 HDPE PIPE 125 0.240
5 HDPE PIPE 140 0.591
6 HDPE PIPE 160 0.161
7 HDPE PIPE 180 0.480
8 HDPE PIPE 200 2.177
HSC Connection
Sno. Total Nos.
1 1318
Other Details
5.67
5.53
5.63
01-Jul-2024
02-Jul-2024