Project Completion Certificate (Ground Water)
Scheme ID: 20093443 Name of Scheme: SHERPUR W/S SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2201 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 28/94.60 SHERPUR 29.17129 77.225
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 410/LPM/66 M SHERPUR 29.17129 77.225
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 125/10 SHERPUR 29.171399 77.224974
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K7 80 0.0166
2 K7 200 0.005
3 K7 150 0.0
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 0.0356
2 HDPE 75 0.2184
3 HDPE 63 4.242
4 HDPE 160 0.0
5 HDPE 125 0.0416
6 HDPE 110 01672
HSC Connection
Sno. Total Nos.
1 388
Other Details
1.52
1.59
1.59
31-Jul-2025
01-Aug-2025