Project Completion Certificate (Ground Water)
Scheme ID: 20093488 Name of Scheme: Arifpur Kheri W/S SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1709 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 19/80 ARIFPUR KHERI 29.093244 77.332704
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 350/ LPM/42 M ARIFPUR KHERI 29.093244 77.332704
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100/12 ARIFPUR KHERI 29.093330 77.332590
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K7 100 0.0267
2 K7 200 0.0039
3 K7 150 0.0059
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 0.3638
2 HDPE 75 0.7906
3 HDPE 63 2.3261
4 HDPE 160 0.0
5 HDPE 140 0.6118
6 HDPE 110 0.0879
HSC Connection
Sno. Total Nos.
1 350
Other Details
1.38
1.50
1.50
31-Dec-2025
01-Jan-2026