| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097023 | Name of Scheme: BANKATA SECOND GP WSS | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1850 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 04-Oct-2024 | Actual Date of Completion (Capex): 25-Mar-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 133.95 | BANAKATA SECOND | 27.064777 | 83.005896 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 400LPM / 44 MTR | BANAKATA SECOND | 27.064777 | 83.005896 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVR HEAD TANK | 125KL / 14 MTR | BANAKATA SECOND | 27.064777 | 83.005896 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 / DI PIPE | 100 | 0.030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PE-100 PE-6 / HDPE PIPE | 75 | 1.082 | |
| 2 | PE-100 PE-6 / HDPE PIPE | 90 | 0.122 | |
| 3 | PE-100 PE-6 / HDPE PIPE | 110 | 0.372 | |
| 4 | PE-100 PE-6 / HDPE PIPE | 125 | 0.380 | |
| 5 | PE-100 PE-6 / HDPE PIPE | 140 | 0.408 | |
| 6 | PE-100 PE-6 / HDPE PIPE | 63 | 5.828 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 369 |