| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20097849 | Name of Scheme: OTI | No. of Villages: 2 | No. of Habitation Covered: 6 |
| Total Population Covered: 2950 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 25-Sep-2024 | Actual Date of Completion (Capex): 28-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Deep Tube well 590 LPM | 12 M / 69.5 M | Oti | 25.731062 | 80.596659 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | 15 HP Submersible Pump | 35.40 m3 / 60 M | Oti | 25.731062 | 80.596659 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Elevated Storage Reservoir | 175 KL / 22 M | Oti | 25.731136 | 80.596559 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-9 | 100 | 0.0238 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PN-6 | 63 | 2.946 | |
| 2 | HDPE PN-6 | 75 | 1.8223 | |
| 3 | HDPE PN-6 | 90 | 2.3319 | |
| 4 | HDPE PN-6 | 110 | 1.4357 | |
| 5 | HDPE PN-6 | 125 | 1.1178 | |
| 6 | HDPE PN-6 | 160 | 1.3174 | |
| 7 | HDPE PN-6 | 180 | 0.6262 | |
| 8 | HDPE PN-6 | 200 | 0.45 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 528 |